Interstate 40 Interchange at State Route 196

Fayette County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW) and Construction. The proposed project for an interchange on Interstate 40 at State Route 196 (Hickory Withe Road) is currently in the Construction phase. The following is a reflection of various aspects of the development phases as they have occurred or will occur for the project.

Environmental Assessment (EA) Approved January 25, 2010
NEPA Public Hearing March 25, 2010
Built Alternative Selected  
Finding of No Significant Impact (FONSI) Approved August 23, 2010
ROW Appraisal/Acquisition  
Construction Contract Awarded December 2, 2016
Estimated Construction Completion Date October 31, 2018

*All forecasted dates are subject to change.