Interstate 40 Interchange at Canada Road

Shelby County

Timeline

PHASE 1: Summer 2014-Fall 2014

  • Construct I-40 Median
  • Construct areas West of Canada Road
  • Construct Connector Road

PHASE 2: Winter 2014-Summer 2015

  • Construct West Half of Bridge
  • Construct I-40 Retaining Walls
  • Close Huff-n-Puff Road at Canada Road

PHASE 3: Summer 2015-Fall 2015

  • Construct West Beverle Rivera Drive
  • Construct areas West of Canada Road
  • Close I-40 Exit 20 Canada Road North Bound

PHASE 4: Winter 2015-Spring 2016

  • Construct Temporary Ramps
  • Construct East Beverle Rivera Drive

PHASE 5: Spring 2016-Fall 2016

  • Construct Eastern Half of Bridge
  • Construct areas East of Canada Road

PHASE 6: Winter 2016-Fall 2017

  • Construct Ramps East of Canada Road
  • Complete work on I-40