Interstate 55 / Crump Boulevard Interchange

Shelby County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction. The following is a reflection of various aspects of these phases as they have occurred or will occur on the Interstate 55 Interchange at E.H. Crump Boulevard and South Riverside Drive in Memphis.

Draft Environmental Impact Statement (DEIS) Approved  
Final Environmental Impact Statement (FEIS) Approved 2011
Record of Decision (ROD) Approved January 25, 2012

*Forecasted dates are subject to change.