Interstate 65 Interchange at State Route 109

Robertson and Sumner Counties

Timeline

All scheduled work is tentative and subject to change.

Bridge Construction

October 2015: Set barrier rail on I-65 inside shoulder

May 2016 to August 2016: Set beams and pour deck for new SR 109 bridge over I-65

July 2017 to August 2017: Remove existing Lake Springs Road bridge over I-65

Ramp Construction

January 2016 to August 2016: Construct ramps A, B, C and D (impacting I-65 North)

June 2016 to January 2017: Construct ramps E, F, G and H (impacting I-65 South)

I-65 Outside Lane Construction

April 2016: Temporary widening of outside shoulders

April 2018 to May 2018: Complete temporary ramp work

July 2015 to June 2019: Complete outside lane construction

I-65 Inside Lane Construction

March 2016 to May 2017: Complete median work

The estimated completion date for this project is June 2019.