State Route 162 Pellissippi Parkway Extension

Blount County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. The following is a reflection of various aspects of these phases as they have occurred or will occur for State Route 162 Pellissippi Parkway Extension.

Draft Environmental Impact Statement (DEIS) Prepared Spring/Summer 2009
DEIS Approved April 14, 2010
Preferred Alternative Selected June 2012
Preferred Alternative Modified (west alignment shift) July 2013
Reevaluation of Final Environmental Impact Statement (FEIS) Approved July 17, 2014
FEIS Approved September 10, 2015
FEIS Notice of Availability Published September 18, 2015
FEIS Public Review Period September 18, 2015 - November 18, 2015

 
 
TDOT/FHWA Review/Response to FEIS Public Review November 18, 2015 - *Spring/Summer 2017
Record of Decision (ROD) Issued August 31, 2017

Please visit the Library Page for this project to review an electronic copy of the DEIS, the FEIS, the 2014 Reevaluation, or the ROD.