State Route 460 (US 64) Somerville Beltway

Fayette County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW) and Construction. The following is a reflection of various aspects of these phases as they have occurred or will occur for the Somerville Beltway project.

NEPA Public Hearing December 2008
Environmental Assessment (EA) Approved September 2009
ROW Meeting April 2011
ROW Appraisals Completed July 2011
ROW Acquisition Completed Forecasted for Winter 2012
Construction Contract Awarded Not funded for construction
Estimated Construction Completion Not funded for construction

*Forecasted dates are subject to change.