State Route 1 Interchange at State Route 10/96

Rutherford County

Timeline

The following timeline has been adjusted to reflect delays associated with utility relocation and design.

January 2014 – March 2014          (Phase 1A)

Shift traffic on Old Fort Pkwy

Remove existing median barrier on CSX bridge

April 2014 – April 2016                   (Phase 1B)

Relocate utilities

Shift traffic on Broad Street and Memorial Blvd

Construct southwest and southeast ramps and retaining walls

Widen east side of Broad Street and south side of Memorial Blvd

Construct new curve alignment to connect College and Burton Streets

Begin reconstruction of Broadmor Boulevard

April 2016 – March 2017                (Phase 2)

Complete secondary retaining wall at southwest ramp

Complete southwest and southeast ramps and shift SR 96/SR 10 eastbound traffic to ramps

Construct northwest and northeast ramps and retaining walls

Widen north side of Old Fort Pkwy

Complete reconstruction of Broadmor Boulevard

March 2017 – December 2017    (Phases 3, 4, and 5)

Complete northwest and northeast ramps and shift SR 96/SR 10 westbound traffic to ramps

Construct bridge

Grade and pave Broad Street, Old Fort Pkwy, and Memorial Blvd

Install traffic signals, landscaping and final pavement markings

The estimated completion date for this project is December 2017.