State Route 112 (Clarksville Highway)

Davidson County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. The following is a reflection of various aspects of these phases as they have occurred or will occur on the improvement of SR 112 (Clarksville Highway).

Future Milestones  
Bat survey Completed Summer 2015
Approval of Final Environmental Document Completed Summer 2015
Funding for ROW Appraisals Only Approved September 2015
Funding for ROW Acquisition Approved February 2016
Construction Funded for FY 2018