State Route 149 / State Route 13

Montgomery County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW), and Construction. The project to widen State Route 149 and State Route 13 in Montgomery County is currently budgeted for construction in FY17. Construction is expected to take approximately three years and will include replacement of the G.G. McClure Bridge over the Cumberland River on SR 13.

The following is a reflection of various aspects of the other project phases as they have occurred or will occur for the proposed improvements.

Engineering Summer 2009
Design Public Meeting June 29, 2010
NEPA Document Approved 2011
Right-of-Way Process (18-24 months) Summer 2012
Construction (30-36 months) Forecasted for late 2017

*All forecasted dates are subject to change.