State Route 16 (US 41-A)

Bedford, Coffee, and Franklin Counties

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. The following is a reflection of various aspects of these phases as they have occurred or will occur on the improvement of the three sections of SR 16.

Project Schedule for SR 16 from SR 64 to SR 276

This section has been divided into two segments in an effort to obtain funding for construction.

Property Acquisitions and Relocations Completed February 15, 2011
SR 64 to Jenkins Road Funded for construction in FY 2018
Jenkins Road to SR 276 Scheduled to let in October 2017

Project Schedule for SR 16 from SR 276 to west of Magnolia Lane

This section has been divided into two segments in an effort to sustain funding for construction.

Property Acquisitions and Relocations Completed January 15, 2010
SR 276 to Rippy Ridge Road  
Construction Contract Awarded December 6, 2013
Construction Completion Date August 2017
Rippy Ridge Road to west of Magnolia Lane  
Construction Contract Awarded April 30, 2010
Construction Completion Date April 2013

Project Schedule for SR 16 from west of Moore-Coffee County line to North Washington Street

Construction Completion Date March 2007