Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way (ROW) and Construction. Proposed improvements to State Route 322 in Monroe County consist of two roadway projects. Below is a reflection of each project phase as they have occurred or will occur for each section of SR 322.

west of Sunnyside Road to State Route 72 (full project length)  
Advanced Planning Report (APR) Approved 2007
Build Alternatives Workshop (Public Meeting) September 2007
NEPA1 Document Approved April 2010
FONSI2 Document Approved December 2010
TDOT Project Evaluation (due to funding limitations) June 2014
Advanced Planning Report (APR) Approved (new) January 2015
Sweetwater-Vonore Road to Sheppard Road  
Preliminary Design (underway) February 2017
Design Public Meeting Forecasted for 1st Quarter 2018
Sheppard Road to State Route 72  
Preliminary Design (underway) April 2016
Design Public Meeting July 2017
ROW Appraisals/Acquisitions (18-24 months to complete) Forecasted for 4th Quarter 2017

*All forecasted dates are subject to change.

  1. NEPA = National Environmental Policy Act (required by Federal Highway Administration to assess environmental impact)
  2. FONSI = Finding of No Significant Impact (required by Federal Highway Administration as part of the National Environmental Policy Act (NEPA) process)

NOTE: The 2007 APR evaluated potential improvements to SR 322 from west of Sunnyside Road to SR 72, approximately 8.5 miles, in Monroe County. Following ongoing funding concerns, TDOT Commissioner John Schroer authorized a reinvestigation of the proposed project in June 2014. The Expedited Project Delivery (EPD) report was approved in January 2015, which allowed the project to move forward.