State Route 6 (Franklin Road)

Williamson County

Construction Timeline

This project was let to construction in June 2017 and has a contract completion date of October 31, 2020.

Preliminary Work
August 2017 – October 2017

  • Traffic Control
  • Erosion Control
  • Clearing

Phase 1
October 2017 - August 2019

  • Utility work/relocation
  • Excavation/Grading
  • Construction of five retaining walls
  • Box culvert Installations
  • Base stone
  • Curb
  • Asphalt paving
  • Sidewalk
  • Swap traffic

Phase 2
August 2019 – October 2020

  • Excavation/Grading
  • Box Culvert Installations
  • Construction of one retaining wall
  • Base stone
  • Curb
  • Asphalt Paving
  • Sidewalk
  • Final Paving
  • Pavement Markings, Signs