State Route 63 (US 25E) Improvements

Campbell and Claiborne Counties

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. Proposed improvements to State Route 63 (US 25E) consist of four roadway projects. Below is a reflection of each project phase as they have occurred or will occur for each section of SR 63.

Campbell County
from Lafollette Urban Boundary to Frontier Road/Woodson Lane  
Environmental Document Approved Forecasted for late summer/early fall 2017
ROW Appraisal/Acquisition (approx 12-18 mos to complete) Pending Environmental Document Approval
Construction Pending ROW Acquisition AND Funding Availability
from Frontier Road/Woodson Lane to Campbell-Claiborne County Line  
Environmental Document Approved Forecasted for late summer/early fall 2017
ROW Appraisal/Acquisition (approx 12-18 mos to complete) Pending Environmental Document Approval
Construction Pending ROW Acquisition AND Funding Availability
Campbell County
from Campbell-Claiborne County Line to Hall  
Environmental Document Approved Forecasted for last summer/early fall 2017
ROW Appraisal/Acquisition (approx 12-18 mos to complete) Pending Environmental Document Approval
Construction Pending ROW Acquisition AND Funding Availability
from West of Old Town Creek to State Route 32 (US 25E)  
Environmental Document Approved Forecasted for last summer/early fall 2017
ROW Appraisal/Acquisition N/A
Construction Pending Environmental Document Approval AND Funding Availability

*All forecasted dates are subject to change.