US 64 Corridor K

Polk County

Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. This project is currently in the Environmental Phase. The following is a reflection of various aspects of these phases as they have occurred or will occur for proposed improvements to US 64/Corridor K.

Activity Completion Date
TESA Concurrence Point (CP) 3 (Preliminary Draft EIS)
Package submitted to TESA agencies
Negotiate Consistency with FS Management Plan
Complete identification of 4F resources and mitigation
Complete programmatic mitigation strategy
TDOT review of document
Summer 2014
CP 3 Review period ends Fall 2014
FHWA Signs Draft Environmental Impact Statement (DEIS) Forecasted for Winter 2015
Prepare and Circulate Signed DEIS Forecasted for Winter 2015
Hold Public Hearing Spring 2015
Identify (Preferred Alternative and Preliminary Mitigation)
Comment period post hearing
Address comments
Submit to FHWA for review and legal sufficiency review
Forecasted for Spring 2016
Final Environmental Impact Statement Signed by FHWA Forecasted for Winter 2016, Spring 2017
Record of Decision Issued Fall 2017

*Forecasted dates are subject to change.