Construction Report for Tennessee Interstates, October 15 - 21, 2009

Thursday, October 15, 2009 | 09:33am
I-24
 
REGION 3 On-Call Guardrail:Thursday October 15 through Wednesday October 21, 8PM-6AM, (each night), There will be one lane closures at various locations on interstates and state routes in Davidson, Rutherford, Dickson, Giles, Robertson, and Williamson Counties for guardrail repair and installation.
 
DAVIDSON COUNTY, TDOT Bridge Repair:Tuesday October 20, 8PM-5AM, Two right lanes on I-24 westbound at exit 47 (Spring Street) between mile marker 46.6 and 47.2 will be closed for bridge deck repair. One lane will remain open on I-24 and the ramp to Spring Street will remain open.
 
DAVIDSON and WILLIAMSON COUNTIES, ITS Phase III:
       Thursday October 15 through Wednesday October 21, 9AM-3PM and 7PM-6AM. There will be periodic day and night time shoulder closures at various locations within the areas listed below in order to install devices, perform electrical work, and pole installation.
o    I-24, both directions between Old Hickory Blvd and Bell Road (MM 40 to MM 61)
       Thursday October 15 through Wednesday October 21, 8PM-5AM, There will be periodic short term night time lane closures at the following locations to install device foundations, DMS foundation installation, and shoulder paving.
    • I-24, both directions, between the I-440 Interchange and Old Hickory Blvd (MM 52 and MM 62), 2-3 lanes remain open (multiple locations for foundation installation.)
 
TDOT Maintenance:
       DAVIDSON COUNTY,
o    Thursday October 15 through Wednesday October 21, 9AM-3PM, (excluding weekends), There will be possible lane closures at various locations in Davidson County in order to patch potholes on an as needed basis.
o    Thursday October 15 through Wednesday October 21, 9AM-3PM, (excluding weekends), There will be mobile operations in various locations in Davidson County for vegetation control. This will affect the shoulders or outside lanes.
       Rutherford County
o    Thursday October 15, 7PM-12AM, There will be one lane closed on I-24 westbound in Rutherford County between mile marker 73 and mile marker 74 in order to patch potholes.  One lane will remain open.
 
THOMAS & ASSOCIATES: Thursday October 15 through Wednesday October 21, each day, 2PM, There will be rolling roadblocks on I-24 eastbound and westbound near Waldron Rd. (Exit 64) for blasting. Local police officers will be utilized for this operation.
 
COFFEE COUNTY, I-24 resurfacing project from Noah Fork Creek (LM 3.45/MM100) to US-41 (LM 8.77/MM105): (Recovery Act Project)The contractor will have lane closures from 7:00 PM to 6:00 AM the following morning to perform resurfacing activity. One lane will be maintained in both directions at all times. Estimated completion date is November 2009.
 
COFFEE COUNTY, I-24 cable guardrail project from MM 102 to MM 105:  The contractor will have lane closures on I-24 East to install cable guardrail between 8:00 PM and 6:00 AM. One lane will be maintained in both directions at all times. Estimated project completion date is October 2009.
 
COFFEE COUNTY, I-24 resurfacing project from SR-55 (LM 14.72/MM111) to the Arnold Engineering Development Center (LM 20.78/MM117): (Recovery Act Project) The contractor will have lane closures from 7:00 PM to 6:00 AM the following morning to perform resurfacing activity. One lane will be maintained in both directions at all times. Estimated completion date is October 2009.
 
MARION COUNTY, I-24 resurfacing from US-72/SR-27/SR-150 (LM 17.61) at MM 152 to the Tennessee River (LM 25.84) at MM 161: (Recovery Act Project) The contractor will have lane closures between the hours of 7:00 PM to 6:00 AM the following morning to perform resurfacing activities. One lane will be maintained in both directions at all times. Estimated completion date is December 2009.
 
HAMILTON COUNTY, I-24 SR-29 construction of an intelligent transportation system on various interstate and state routes in and near Chattanooga: The contractor will implement shoulder closures throughout this report period within the project area on weekdays between the hours of 9:00 AM and 4:00 PM and anytime on the weekend as part of the ITS construction. They will also implement the following lane closures:
Thursday, October 15, 2009 & Friday, October 16, 2009: Night Work 10:00 PM until 5:00 AM
       I-24 WB @ MM 181.5 to 182.5 – Right lane closure. Two lanes are to remain open.
Friday, October 16, 2009 at 10:00 PM through Saturday, October 17, 2009 at 10:00 AM: WEEKEND CLOSURES
       I-24 EB @ MM 181.5 to 182.5 – Right lane closure. Two lanes are to remain open.
       I-24 WB @ MM 181.5 to 182.5 – Right lane closure. Two lanes are to remain open.
Saturday, October 17, 2009 at 10:00 PM through Sunday, October 18, 2009 at 10:00 AM: WEEKEND CLOSURES
       I-24 EB @ MM 181.5 to 182.5 – Right lane closure. Two lanes are to remain open.
       I-24 WB @ MM 181.5 to 182.5 – Right lane closure. Two lanes are to remain open.
Monday, October 19, 2009 through Wednesday, October 21, 2009: Night Work 10:00 PM until 5:00 AM
       I-24 EB @ MM 181.5 to 182.5 – Right lane closure. Two lanes are to remain open.
       I-24 WB @ MM 181.5 to 182.5 – Right lane closure. Two lanes are to remain open.
Estimated completion date is December 2010.
 
HAMILTON COUNTY, I-75 / I-24 sign installation project at various locations in the vicinity of the 1-24 / I-75 Split, including paving: This project is complete. Estimated completion date is October 2009.
 
 
I-124
 
HAMILTON COUNTY, US-27 (I-124) repair of 15 bridges from I-24 (MM 0) to the Olgiati Bridge (MM 2.0):  The northbound lanes are all open to traffic. Throughout this report period the contractor will have nightly lane closures on US-27 South from 7:00 PM until 6:00 AM the following morning for bridge deck repairs. One lane will be maintained at all times during this nightly work. Two lanes of traffic will be maintained on US-27 South daily from 6:00 AM until 7:00 PM. The entrance ramp from west MLK Blvd. onto US-27 (I-124) South is now reopened. Estimated completion date is October 2009.
 
 
I-26
 
WASHINGTON COUNTY, I-26 Bridge over Boones Creek Road (SR 354) (Bridge Repair): The contractor is continuing this bridge repair project. This work is weekend work and will cause a reduction in lanes on SR 354 and closure of the outside shoulder on I-26 Eastbound. Work is to take place from Friday nights at 7:00 pm to Monday at 6:00 am. Motorists please use caution in this area.
 
 
I-40
 
SHELBY COUNTY, Seismic Retrofit on the bridge on I-40 over the Mississippi River:
       Thursday, October 15 6AM until 7PM. There will be one lane closed Westbound (two lanes open), one lane closed Eastbound (two lanes open).
        Thursday, October 15 7PM until Friday, October 16 6AM. There will be two lane closedWestbound (one lane open), one lane closed Eastbound (two lanes open).
        Friday, October 16 6AM until 7PM. There will be one lane closed Westbound (two lanes open), one lane closed Eastbound (two lanes open).
       Friday, October 16 7PM through Monday, October 19 6AM. There will be two lane closedWestbound (one lane open), one lane closed Eastbound (two lanes open).
       Monday, October 19 6AM until 7PM.  There will be one lane closed Westbound (two lanes open), one lane closed Eastbound (two lanes open).
       Monday, October 19 7PM until Tuesday October 20 6AM. There will be two lane closedWestbound (one lane open), one lane closed Eastbound (two lanes open).
       Tuesday October 20 6AM until 7PM. There will be one lane closed Westbound (two lanes open), one lane closed Eastbound (two lanes open).
       Tuesday, October 20 7PM until Wednesday October 21 6AM. There will be two lane closed Westbound (one lane open), one lane closed Eastbound (two lanes open).
       Wednesday October 21 6AM until 7PM. There will be one lane closed Westbound (two lanes open), one lane closed Eastbound (two lanes open).
NOTE: At least one lane of the westbound Entrance Ramp located east of the arch spans (Ramp I L) will be open at all times. Any delays due to weather will cause these closures to be canceled or postponed to the next day.
 
Region IV Maintenance:Monday, October 19 through Friday, October 23. There will be possible lane closures at various locations in Region IV in order to patch potholes on an as needed basis.
 
 
FAYETTE COUNTY, Bridge Repair (5) on I-40: Friday, October 16 8PM through Monday, October 19 6AM, westbound and eastbound. The contractor will have lane closures in order to place overlay on the decks on 4 bridges. One lane will be maintained in both directions at all times. 
 
REGION 4, Installation of Longitudinal Cable Barrier Rail on various Interstate & State Routes
       SHELBY COUNTY
o    Sunday, October 18 through Thursday, October 22, westbound I-40 MM 20.88 to MM 22.38 from8PM-6AM nightly. The contractor will have one lane maintained at all times.
o    Tuesday, October 20, through Thursday, October 22. I-40 westbound MM 29.5 to MM 22.0 from 8PM-6AM, nightly. The contractor will have one lane maintained at all times.
       SHELBY/FAYETTE COUNTIES
o    Sunday, October 18 through Thursday, October 22, westbound I-40 MM 21.88 to MM 27.5 from8PM-6AM nightly. The contractor will have one lane maintained at all times.
       MADISON COUNTY
o    Sunday, October 18 through Thursday, October 22, I-40 eastbound MM 76.05 to MM 77.00 near SR-223 from 8PM-6AM nightly. The contractor will have one lane maintained at all times.
o    Sunday, October 18 through Thursday, October 22, I-40 westbound MM 75.05 to MM 76.00 near SR-223 from 8PM-6AM nightly. The contractor will have one lane maintained at all times.
       HENDERSON COUNTY
o    Tuesday, October 13 through Thursday, October 15, I-40 eastbound MM 113.0 to MM 115.0 from 8PM-6AM nightly. The contractor will have one lane maintained at all times.
o    Sunday, October 18 through Thursday, October 22, I-40 eastbound MM 100.50 to MM 101.00 from 8PM-6AM nightly. The contractor will have one lane maintained at all times.
o    Wednesday, October 21 and Thursday, October 22. I-40 westbound MM 100.5 to MM 99.0 from 8PM-6AM nightly. The contractor will have one lane maintained at all times.
       DECATUR COUNTY
o    Monday, October 19 and Tuesday, October 20. I-40 westbound MM 125.5 to MM 124.5from 8PM-6AM nightly. The contractor will have one lane maintained at all times.
o    Thursday, October 15 and Friday, October 16, I-40 westbound MM 126.0 to MM 125.0from 8PM-6AM nightly. The contractor will have one lane maintained at all times.
       BENTON COUNTY:  Sunday, October 18. I-40 westbound MM 132.0 from 8PM-6AM nightly. The contractor will have one lane maintained at all times.
 
REGION 4, On-Call Guardrail Repair:
       SHELBY COUNTY
o    Monday October 19 8PM-10PM. I-40 Eastbound near Watkins Avenue, one lane closed, two lanes open.
o    Monday, October 19 and Tuesday, October 20, 10PM-2AM. I-40 Eastbound betweenExit 12/Sycamore View and Exit 14/Whitten Road, one lane closed, two lanes open.
       FAYETTE COUNTY
o    Thursday, October 15, 12PM-5PM. I-40 Eastbound and Westbound “On” ramps @ Exit 35/SR-59 will remain open, but may be impeded.
 
REGION 3 On-Call Guardrail:Thursday October 15 through Wednesday October 21, 8PM-6AM, (each night), There will be one lane closures at various locations on interstates and state routes in Davidson, Rutherford, Dickson, Giles, Robertson, and Williamson Counties for guardrail repair and installation.
 
DAVIDSON COUNTY, ITS Phase III:
       Thursday October 15 through Wednesday October 21, 9AM-3PM and 7PM-6AM. There will be periodic day and night time shoulder closures at various locations within the areas listed below in order to install devices, perform electrical work, and pole installation.
o    I-40, both directions between US-70 and Old Hickory Blvd (MM 196 to MM 222)
       Thursday October 15 through Wednesday October 21, 8PM-5AM, There will be periodic short term night time lane closures at the following locations to install device foundations, DMS foundation installation, and shoulder paving.
o    I-40, both directions, between the I-24 Interchange and Old Hickory Blvd (MM 213 to MM 222), 3 lanes remain open (multiple locations for foundation installation).
o    I-40, Westbound, between Memphis Bristol (US70) and east of Charlotte Pike (MM 196 to MM 203), 2 lanes remain open. (multiple locations for foundation installation).
o    I-40, both directions, between Donnelson Pike and Briley Pkwy (MM 216 to MM 215).
    • Friday October 9th 8pm to Monday October 12th 6am, 1 left lane in both directions, 4 lanes to remain open.
       Road Closures: October 17th 11pm to October 18th 9am (if rained out, repeat October 24th), periodic road closures to install DMS signs over the highway at the following locations:
o    I-40, Westbound, MM 202.5, (West of White Bridge Rd)
o    I-40, Eastbound, MM 198, (West of Old Hickory Blvd)
 
DAVIDSON COUNTY, Resurfacing on I-40 from US 70S to Charlotte Pike:(Recovery Act Project)
       Thursday October 15 through Wednesday October 21, 8PM-5AM, (excluding Saturday), There will be alternating lane closures on I-40 in both directions in order to mill and pave the roadway. One lane will remain open.
 
DAVIDSON COUNTY, I-40 and Robertson Road Interchange:(Recovery Act Project)
       Thursday October 15 through Wednesday October 21, 8AM-3PM, On the I-40 Westbound on-ramp at White Bridge flagging of traffic will occur to allow construction trucks to enter and exit the work zone. Traffic will be stopped only long enough for trucks to enter or exit the work zone. Flagging operations will be occurring throughout the day.
       Twin Street and Snyder Avenue will be closed starting Monday, October 5, 2009. Traffic will be detoured to Stevenson Street. Only local traffic will be allowed on Twin Street.
 
DAVIDSON COUNTY, TDOT Utilities:  
       Tuesday October 20 through Thursday October 22,7PM-6AM, On I-40 W.B.L., on the outside lane at Arlington Avenue Overpass, Davidson County.  This request, by N.E.S., is to repair underground conduit for power cables serving interstate lighting.
       Sunday October 18, 7AM-2PM, On I-40/Davidson Road, Davidson County.  This request, by N.E.S., is for transferring wires to new poles.  Four rolling stop blocks are expected.
 
DAVIDSON COUNTY, Installation of an Overhead Sign on I-40 (Lu, Inc.)Thursday October 15 through Wednesday October 21, 8PM-5AM, (excluding weekends), There will be one lane of I-40 eastbound and westbound closed at MM 209 in order to prepare for new sign foundation. Two lanes will remain open.
 
TDOT Maintenance:
       DAVIDSON COUNTY
Thursday October 15 through Wednesday October 21, 9AM-3PM, (excluding weekends), There will be possible lane closures at various locations in Davidson County in order to patch potholes on an as needed basis.
Thursday October 15 through Wednesday October 21, 9AM-3PM, (excluding weekends), There will be mobile operations in various locations in Davidson County for vegetation control. This will affect the shoulders or outside lanes.
       Smith County
o    Thursday October 15, 9AM-4PM, There will be one lane closed on I-40 eastbound in Smith County at mile marker 254 in order to install a French drain pipe.  One lane will remain open.
 
PUTNAM COUNTY, I-40 resurfacing project from MM 267.25 to MM 274: (Recovery Act Project) The contractor will have lane closures to perform stone and striping operations between 7:00 PM and 6:00 AM. One lane will be maintained in both directions at all times. Estimated project completion date is October 2009.
 
CUMBERLAND COUNTY, I-40 resurfacing from MM 306 to MM 311 (Plateau Road): Work on this project is complete and awaiting final inspection. Estimated completion date is October 2009.
 
KNOX COUNTY, I-40 East & West at West Hills (Exit 380): On Sunday night, October 18, 2009 thru Wednesday night, October 21, 2009 between the hours of 8 p.m. and 6 a.m. the following morning motorist should be alert for lane closures thru this area as crews perform roadway maintenance. Motorists should be alert potential long delays and use extreme caution through this area. Lane closures on Sunday night will begin at 6 p.m.
 
KNOX COUNTY, I-40 East & West between Papermill (Exit 383) & Walker Springs (Exit 379): On Monday night, October 19, 2009 thru Thursday night, October 22, 2009 between the hours of 8 p.m. and 6 a.m. the following morning motorist should be alert for lane closures thru this area as crews perform roadway maintenance. Motorists should be alert potential long delays and use extreme caution through this area. 
 
 
I-140
 
No construction activity to report at this time.
 
 
I-240
 
Region IV Maintenance:Monday, October 19 through Friday, October 23. There will be possible lane closures at various locations in Region IV in order to patch potholes on an as needed basis.
 
REGION 4, On-Call Guardrail Repair:
       SHELBY COUNTY
o    Thursday, October 15 2AM-6AM. I-240 Southbound “On” ramp from Westbound Jackson Avenue, at the I-240/I-40 junction, CLOSED.
o    Thursday, October 15, 8PM-10PM. I-240 Southbound “On” ramp from WestboundJackson Avenue, at the I-240/I-40 junction, CLOSED.
o    Friday, October 16, 12AM-2AM. I-240 Southbound near the I-240/I-55 junction, one lane closed, two lanes open.
o    Friday, October 16, 2AM-6AM. I-240 Eastbound near MM 25 Millbranch, one lane closed, two lanes open.
o    Tuesday, October 20, 2AM-6AM. I-240 Westbound near Exit 25, one lane closed, one lane open.
o    Tuesday, October 20, 8PM-12AM. I-240 Eastbound near Exit 23/Airways Blvdone lane closed, two lanes open.
 
 
I-440
 
REGION 3 On-Call Guardrail:Thursday October 15 through Wednesday October 21, 8PM-6AM, (each night), There will be one lane closures at various locations on interstates and state routes in Davidson, Rutherford, Dickson, Giles, Robertson, and Williamson Counties for guardrail repair and installation.
 
DAVIDSON and WILLIAMSON COUNTIES, ITS Phase III:
       Thursday October 15 through Wednesday October 21, 9AM-3PM and 7PM-6AM. There will be periodic day and night time shoulder closures at various locations within the areas listed below in order to install devices, perform electrical work, and pole installation.
o    I-440, both directions between Hillsboro Pike and I-24 (MM 3 to MM 7)
 
DAVIDSON COUNTY, I-440 Concrete Rehabilitation:(Recovery Act Project)
       Friday October 16, 8PM through Monday October 19, 6AM, I-440 eastbound will be closed from I-40 to I-65 for concrete repairs.
 
 
I-640
 
KNOX COUNTY, I-640 West Flyover Ramp to I-40 East: Beginning on Saturday, October 17, 2009, the flyover ramp from I-640 West to I-40 East will be reduced from two lanes to one around the clock as crews perform bridge repairs. Motorist should be alert for workers present and use extreme caution in this area. The estimated completion date for this project is November 15, 2009.
 
KNOX COUNTY, I-640 West between Millertown Pike (Exit 8) and I-275/75 interchange (Exit 3): On Tuesday night, October 20, 2009 beginning at 8 p.m. motorists should be alert for rolling roadblocks thru this area as crews perform attenuator repairs. During this time the ramp from Broadway to I-640 West will be temporarily closed. Motorist should be alert for sudden stops, expect potential delays, and use extreme caution in this area.
 
 
I-55
 
Region IV Maintenance:Monday, October 19 through Friday, October 23. There will be possible lane closures at various locations in Region IV in order to patch potholes on an as needed basis.
 
SHELBY COUNTY, I-55:resurfacing at Mississippi State Line to Nonconnah Creek.
       Thursday, October 15 through Wednesday, October 21: I-240 northbound and southboundfrom 7PM-6AM, nightly. The contractor will have lane closures in order to perform paving operations. One lane will be maintained at all times. Ramps may be impeded or closed at certain times.
       Thursday, October 15 through Wednesday, October 21: I-55 northbound and southboundfrom 7PM-6AM, nightly. The contractor will have lane closures in order to perform paving operations. One lane will be maintained at all times. Ramps may be impeded or closed at certain times.
 
SHELBY COUNTY, I-55 at Mallory Avenue: Widening of exist bridges, 3 lanes reduced to 2 each direction. Southbound will be shifted to the newly widening roadway. Traffic switched to new roadway. There will no longer be access to Mallory (Exit 9) from Northbound I-55. Use Third St (Exit 7) detour to Mallory. Riverside Drive from Mallory Avenue to Devant Street is closed indefinitely.  This existing section of roadway will be new location of the northbound I-55 entrance ramp. Use the newly constructed Riverport Road extension as an alternate route.
       Thursday, October 15 through Wednesday, October 21, northbound from 9AM-3PM. The contractor will haveintermittent lane closures to work on interstate bridge construction (Bridges 3 & 4). One lane will be maintained in both directions at all times.
 
REGION 4, Installation of Longitudinal Cable Barrier Rail on various Interstate & State Routes
       SHELBY COUNTY
o    Sunday, October 18 and Monday, October 19. I-55 northbound MM 6.5 to MM 10.3 from8PM-6AM, nightly. The contractor will have one lane maintained at all times.
o    Monday, October 19 and Tuesday, October 20. I-55 northbound MM 6.5 to MM 10.3from 8PM-6AM, nightly. The contractor will have one lane maintained at all times.
 
 
I-155
 
DYER COUNTY, I-155 Bridge Repair: bridge repairs, over Mississippi River.  Northbound and Southbound shoulders are closed. Monday, October 19 7AM through Thursday, October 22 7AM (24 hours), westbound and eastbound. The contractor will have lane closures in order to re-paint the steel structure and perform concrete repairs. One lane will be maintained in both directions at all times. Once the contractor starts he has to keep going till he is finished.
 
 
 
I-65
 
REGION 3 On-Call Guardrail:Thursday October 15 through Wednesday October 21, 8PM-6AM, (each night), There will be one lane closures at various locations on interstates and state routes in Davidson, Rutherford, Dickson, Giles, Robertson, and Williamson Counties for guardrail repair and installation.
 
REGION 3 Relensing of Snowplowable Markers at various locations on Interstate 65
       Thursday October 15 through Wednesday October 21, 8PM-6AM, There will be mobile lane closures at the following locations in order to replace snowplowable markers.
o    Robertson I-65 MM 104 to Kentucky State Line
o    Marshall I-65 MM 22.7 to 35.5
o    Maury I-65 MM 35.5 to 53.1
o    Williamson I-65 MM 53.1 to 69.4
 
DAVIDSON COUNTY, TDOT Utilities:  
       Sunday October 18, 7AM-3PM, On I-65 and Dickerson Pike Interchange, Davidson County.  This request, by N.E.S., is for adding a strand and fiber optic cable across I-65.  Two rolling stop blocks are expected.
       Sunday October 18,7AM-6PM, On I-65 and Old Hickory Blvd. exit in Brentwood, Davidson County.  This request, by N.E.S., is for transfers and adding fiber optic cable over I-65.  Eight rolling stop blocks are expected.
       Sunday October 18, 7AM-8AM, On I-65, 1/4 mile North of Harding Road overpass, Davidson County.  This request, by N.E.S., is for dropping four conductors from existing utility poles.  One rolling stop block is expected.
 
DAVIDSON and WILLIAMSON COUNTIES, ITS Phase III:
       Thursday October 15 through Wednesday October 21, 9AM-3PM and 7PM-6AM. There will be periodic day and night time shoulder closures at various locations within the areas listed below in order to install devices, perform electrical work, and pole installation.
o    I-65, both directions between Concord Rd and Long Hollow Pike (MM 70 to MM 97)
       Thursday October 15 through Wednesday October 21, 8PM-5AM, There will be periodic short term night time lane closures at the following locations to install device foundations, DMS foundation installation, and shoulder paving.
    • I-65, both directions, between Concord Rd and the I-440 Interchange (MM 71 to MM 80), 2-3 lanes remain open (multiple locations for foundation installation).
       Saturday and Sunday, 6AM-12PM, Request for daytime lane closure on I-65 to set 50’ poles in the following location.
    • I-65 SB, South of Harding Place (MM 77-78)
    • I-65 NB, South of Harding Place (MM 76-77)
    • I-65 NB, North of Old Hickory Blvd (MM 75-76)
    • I-65 NB, South of Old Hickory Blvd (MM 73-74)
 
TDOT Maintenance
       DAVIDSON COUNTY:
o    Thursday October 15 through Wednesday October 21, 9AM-3PM, (excluding weekends), There will be possible lane closures at various locations in Davidson County in order to patch potholes on an as needed basis.
o    Thursday October 15 through Wednesday October 21, 9AM-3PM, (excluding weekends), There will be mobile operations in various locations in Davidson County for vegetation control. This will affect the shoulders or outside lanes.
o    Thursday October 15 through Wednesday October 21, 7PM-5AM, (excluding weekends), There will be various lane closures on I-65 both directions between Dickerson Road and Trinity Lane to repair areas of the roadway.
       Robertson County
o    Thursday October 15 through Wednesday October 21, 8PM-6AM, (excluding weekends), There will be one lane closed on I-65 northbound and southbound in Robertson County between mile marker 112.0 and mile marker 114.0 in order to mill and pave to repair potholes.  One lane will remain open.
 
 
I-75
 
HAMILTON COUNTY, I-75 / I-24 sign installation project at various locations in the vicinity of the 1-24 / I-75 Split, including paving: This project is complete. Estimated completion date is October 2009.
 
HAMILTON COUNTY, I-75 construction of an intelligent transportation system on various interstate and state routes in and near Chattanooga: The contractor will implement shoulder closures throughout this report period within the project area on weekdays between the hours of 9:00 AM and 4:00 PM and anytime on the weekend as part of the ITS construction. They will also implement the following lane closures:
       Thursday, October 15, 2009 & Friday, October 16, 2009: Night Work 10:00 PM until 5:00 AM
o    I-75 NB & SB @ MM 10.4 – Left lane closure. One lane is to remain open.
o    I-75 NB & SB @ MM 2.5 – Double Left lane closure. Two lanes are to remain open.
       Friday, October 16, 2009 at 10:00 PM through Saturday, October 17, 2009 at 10:00 AM: WEEKEND CLOSURES
o    I-75 NB & SB @ MM 2.5 – Left lane closure. Three lanes are to remain open.
       Saturday, October 17, 2009 at 10:00 PM through Sunday, October 18, 2009 at 10:00 AM: WEEKEND CLOSURES
o    I-75 NB & SB @ MM 2.5 – Left lane closure. Three lanes are to remain open.
       Sunday, October 18, 2009 at 10:00 PM through Monday, October 19, 2009 at 5:00 AM: WEEKEND CLOSURES
o    I-75 NB & SB @ MM 2.0 – Left lane closure. Three lanes are to remain open.
       Monday, October 19, 2009 through Wednesday, October 21, 2009: Night Work 10:00 PM until 5:00 AM
o    I-75 NB & SB @ MM 2.5 – Left lane closure. Three lanes are to remain open.
Estimated completion date is December 2010.
 
HAMILTON COUNTY, I-75 widening project from 1.1 miles south of Lee Highway (SR-2, US-11) to 1.2 miles north of Lee Highway (SR-2, SR-11): The contractor will only need a lane closure on I-75 during this period if there is an emergency situation which requires maintenance of items. If a lane closure is required, one lane of traffic will remain open at all times. 
       The contractor will have lane closures on Hill Top Road, Hunter Road, Snow Hill Road, Mountain View Road, Lee Highway, and Old Lee Highway from 8:30 AM until 7:00 PM to construct new roadway and accommodate bridge demolition and gas line construction. However, the contractor must move off the roadway from 2:30 PM until 3:00 PM each day during the shift change at Miller Industries. One lane will remain open at all times.
       The temporary slip ramp to I-75 South is now open at Hilltop Drive. Drivers needing to access I-75 South from the Hunter Road area can now do so by using the newly opened ramp at hilltop Drive, avoiding the Ooltewah interchange altogether. The slip ramp has its own dedicated lane onto the interstate so drivers accessing I-75 South via ramp are not required to merge when entering the interstate. The temporary ramp will be in place for the remainder of the project.
       The bridge on Old Lee highway is now open to traffic. Later in the year the contractor will place a final layer of asphalt on the roadway. The truck station located at the end of the project on I-75 South is now closed and will remain closed for the duration of the project.
Estimated completion date is December 2010.
 
KNOX COUNTY, I-75 North and South between I-640 and Callahan Drive (Exit 110): (Recovery Act Project)  On Thursday night October 15, 2009 motorists should be alert for possible mobile lane closures and rolling road blocks on I-75 between I-640 and Callahan Drive between the hours of 8 p.m. (Southbound) 9 p.m. (Northbound) and 6 a.m. the following morning as crews install permanent pavement markings through this resurfacing project. If work is not completed on Thursday night, October 15, 2009, crews will resume work on Saturday night, October 17, 2009 between midnight and 8 a.m. Sunday morning, October 18, 2009.   Motorists should be alert potential long delays and use extreme caution through this area.
 
CAMPBELL COUNTY, I-75 North between Mile Markers 142 and 145:On Thursday night, October 15, 2009, and Sunday night, October 18, 2009 through Thursday night, October 22, 2009 between the hours of 8 p.m. and 6 a.m. the following morning, motorists should be alert for a lane closure on I-75 North through this area as crews install longitudinal cable barrier. Motorists should be alert for workers present and use caution in this area.
 
CAMPBELL COUNTY, I-75 South between Mile Markers 144 and 147:On Thursday night, October 15, 2009, and Sunday night, October 18, 2009 through Thursday night, October 22, 2009 between the hours of 8 p.m. and 6 a.m. the following morning, motorists should be alert for a lane closure on I-75 North through this area as crews install longitudinal cable barrier. Motorists should be alert for workers present and use caution in this area.
 
 
I-275
 
No construction activity to report at this time.
 
 
I-81
 
SULLIVAN COUNTY, I-81 between South of Exit 63 and North of Exit 69 (Resurfacing): The contractor is continuing this resurfacing project. This work will cause temporary lane closures at night between 7:00 pm and 6:00 am Sunday through Friday. Motorists are asked to use caution in this area.
 
 
Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity.
 
Most work is weather dependent and subject to change due to inclement weather.
 
TDOT is now on Twitter: 
       For statewide: www.twitter.com/TN511
       For Knoxville, the Tri-Cities, and Upper East Tennessee: www.twitter.com/knoxville511.
       For Chattanooga, Cookeville, Crossville, and the Cumberland Plateau: www.twitter.com/chattanooga511
       For Nashville, Clarksville, Murfreesboro, and Middle Tennessee: www.twitter.com/nashville511
       For Memphis, Jackson, and West Tennessee: www.twitter.com/memphis511

Motorists are reminded to use all motorist information tools responsibly. Drivers should refrain from texting, tweeting, or using a mobile phone while operating a vehicle. TDOT advises drivers to "Know before you go!" by checking traffic conditions before leaving for your destination. 

Press Releases | Road Closures