Interstate Construction Report for May 20-26, 2010

Thursday, May 20, 2010 | 11:03am
I-24
 
TDOT Maintenance:
       Davidson County
o    Thursday May 20 through Wednesday May 26, 9AM-3PM, There will be possible lane closures at various locations in Davidson County in order to patch potholes on an as needed basis.
o    Thursday May 20 through Wednesday May 26, 9AM-3PM, There will be mobile operations in various locations in Davidson County for vegetation control. This will affect the shoulders or outside lanes. 
o    Saturday May 22 and Sunday May 23, 6AM-2PM There will be rolling roadblocks in the left lane at the following locations in Davidson County for cleaning grates and removing vegetation:
§ I-24 eastbound from mile marker 53 to mile marker 63
 
REGION 3 On-Call Guardrail:Thursday May 20 through Tuesday May 25, 8PM-6AM, (each night), There will be one lane closures at various locations on interstate routes in Davidson County for guardrail repair and installation.
 
REGION 3 Installation of Cable Barrier:
       Thursday May 20 through Wednesday May 26, 8PM-6AM, There will be one lane closed on I-24 eastbound and westbound
o    MM 34-45 in Davidson County
o    MM 73-76 and MM 95-96 in Rutherford County
o    One lane will remain open.
 
DAVIDSON WILLIAMSON COUNTY, ITS Phase III:
       Thursday May 20 through Wednesday May 26, 9AM-3PM and 7PM-6AM, There will be periodic day and night time shoulder closures at various locations within the areas listed below in order to install devices, perform electrical work, and pole installation.
o    I-24, both directions, between Old Hickory Blvd and Bell Rd (MM 40 to MM 61)
 
DAVIDSON COUNTY, Resurfacing on I-24 from Haywood Lane to Rutherford Co. line:Thursday May 20 through Wednesday May 26, 8PM-6AM, There will be alternating one lane closure on I-24 eastbound and westbound in order to perform concrete and guardrail repairs.
 
HAMILTON, BRADLEY, and MARION COUNTIES, I-75 / I-24 / SR-153 / SR-29 construction of an intelligent transportation system on various interstate and state routes in and near Chattanooga: The contractor will implement shoulder closures throughout this report period within the project area on weekdays between the hours of 9:00 AM and 4:00 PM and anytime on the weekend as part of the ITS construction. On weekdays during non-peak hours, the contractor will have a right lane closure on SR-29 South at MM 2.5. Three lanes are to remain open with third available lane used as acceleration lane for on-ramp from Manufacturers Road. There also may be weeknight lane closures throughout the project between the hours of 10:00 PM and 5:00 AM, nighttime weekend lane closures between the hours of 10:00 PM and 10:00 AM, and intermittent temporary stoppages of traffic (less than 15 minutes) at various locations throughout the project area to allow the contractor to perform ITS work. THP will assist with traffic control. Estimated completion date is December 2010. 
 
 
I-124
 
No construction activity to report at this time.
 
 
I-26
 
SULLIVAN & WASHINGTON COUNTY, I-26 East and West at various locations between Mile Markers 5 and 12:On Monday night, May 24, 2010 motorists should be alert for possible lane closures through this area between 8 p.m. and 6 a.m. the following morning as crews repair guardrail. Motorists should be alert for workers present and use extreme caution traveling through this area.
 
SULLIVAN & WASHINGTON COUNTY, I-26 East and West at various locations between Mile Markers 8 and 20:Motorists should be alert for possible lane closures through this area as crews install median cable barrier. Motorists should be alert for workers present and use extreme caution traveling through this area.
 
 
I-40
 
SHELBY COUNTY, Seismic Retrofit on the bridge on I-40 over the Mississippi River
       Various closures for existing six lane cross-section (arch spans):
o    Wednesday May 19 12AM through Friday May 21, 7PM: There will be one eastbound & one westbound lane closed.
o    Friday May 21, 7PM through Monday May 24, 6AM: There will be one eastbound lane & two westbound lanes closed.
o    Monday May 24, 6AM through Wednesday May 26: There will be one eastbound & one westbound lane closed.
       Various closures for existing four lane section (east of the arch spans):
o    Friday May 21, 7PM through Monday May 24, 6AM: There will be one westbound lane closed.
o    Monday May 24, 7PM through Tuesday May 25, 6AM: There will be one westbound lane closed.
       Friday May 21, 7PM through Monday May 24, 6AM: The westbound entrance ramp (Ramp IL/D) located just east of the arch spans will be closed.
 
REGION IV Maintenance
       Wednesday May 19 through Wednesday May 26, 8AM-4PM, There will be possible lane closures at various locations in Region IV in order to patch potholes on an as needed basis.
       Monday May 24 through Wednesday May 26, 9AM-3PM, There will possible lane closures at various locations in Region IV in order to fix washed out areas.
 
HENDERSON COUNTY Design-Build on SR-104 over I-40 MM 101.00: Saturday May 22 & Sunday May 23, 6AM-8PM: There will be one lane closures on I-40 eastbound & westbound to divert traffic onto the ramps over S.R. 104 & back to I-40. This lane closure is required for Phase 2 demolition of the old existing SR-104 bridge over I-40. S.R. 104 & the bridge located @ MM 101 will be closed to local traffic entering I-40. Traffic will be flagged on S.R. 104. THP will assist with lane closures on I-40.
 
DECATUR COUNTY-Resurfacing on I-40 at CARROLL CO. line LM-0.00 to the BENTON CO. line LM-5.67:Sunday May 23 through Friday May 28, 7PM-6AM, There will be night time lane closures eastbound and westbound (MM 121 to MM 126) in order to perform paving operations. One lane will remain open in each direction.
 
TDOT Maintenance:
       Davidson County
o    Thursday May 20 through Wednesday May 26, 9AM-3PM, There will be possible lane closures at various locations in Davidson County in order to patch potholes on an as needed basis.
o    Thursday May 20 through Wednesday May 26, 9AM-3PM, There will be mobile operations in various locations in Davidson County for vegetation control. This will affect the shoulders or outside lanes. 
o    Thursday May 20 through Wednesday May 26, 7PM-5AM, I-40 eastboundand westbounddowntown ramp work at Charlotte Ave., Church St., Broadway and Demonbreun St. exits will result in lane shifts. 
                   Dickson County, Hickman, & Humphreys Counties
o    Thursday, May 20 through Wednesday, May 26, 9AM-3PM, (excluding weekends), There will be possible lane closures at various locations on I-40 in Dickson, Hickman, and Humphreys Counties in order to patch potholes on an as needed basis.
 
REGION 3 On-Call Guardrail:Thursday May 20 through Tuesday May 25, 8PM-6AM, (each night), There will be one lane closures at various locations on interstate routes in Davidson, Wilson, and Smith Counties for guardrail repair and installation.
 
TDOT Utilities
       Sunday May 23, 6AM-4PM, On I-40 & I-65, 300' south of Jo Johnson Ave. overpass near MM 209 in Davidson County. This request by Nashville Electric Service for transferring transmission lines and pulling conductor strands over the interstate. Four rolling stop blocks are expected. Six police cars will be present.
       Sunday May 23, 7AM-9AM, At the I-40 & Elm Hill Overpass in Davidson County This request by Comcast, for a overhead aerial crossing for one strand & fiber optic cable. Two rolling stop blocks are expected. Eight police cars will be present.
 
DAVIDSON COUNTY, ITS Phase III:
       Thursday May 20 through Wednesday May 26, 9AM-3PM and 7PM-6AM, There will be periodic day and night time shoulder closures at various locations within the areas listed below in order to install devices, perform electrical work, and pole installation.
       I-40, both directions, between US 70 and Old Hickory Blvd (MM 196 to MM 222)
 
DAVIDSON COUNTY, I-40 and Robertson Road Interchange:(Recovery Act Project)
       Thursday May 20 through Wednesday May 26, 10AM-10:15 AM and 1PM to 1:15 PM, (excluding weekends), There will be rolling roadblocks for both eastbound and westbound I-40 for blasting on the north side of I-40.
       Thursday May 20 through Saturday May 22, 8PM-5AM, There will be alternating lane closures on I-40 eastbound and westbound at the White Bridge Rd. overpass for the removal of conduit. No more than two lanes in one direction will be closed at a time.
 
DAVIDSON COUNTY, Bridge Repair on New Hope Rd. over I-40:Thursday May 20 and Friday May 21, 8PM-5AM, There will be alternating lane closures on I-40 (MM221.8) at New Hope Rd. in order to texture coat the bridge.
 
PUTNAM COUNTY, I-40 rockfall mitigation at various locations: The contractor will have a right shoulder closure in order to work on the project. Nighttime lane closures will be needed to set barrier rail to route traffic around construction activities. One lane will be maintained in both directions at all times. Each lane has been narrowed to a 10 foot width.  The possibility exists daily for a potential rolling road block due to rock blasting activities.  Emergency lane closures on an as needed basis will be implemented during daylight hours to accommodate pothole repair.  All other lane closures will be from 7:00 PM to 6:00 AM. Estimated completion date is July 2010. 
 
PUTNAM COUNTY, I-40 resurfacing from MM 300 to MM 304: The contractor will have nighttime lane closures from 7:00 PM until 6:00 AM the following morning for cold planing and resurfacing activities. Estimated completion date is July 2010. 
 
CUMBERLAND COUNTY, I-40 resurfacing from MM 304 to MM 306: The contractor will have nighttime lane closures from 7:00 PM until 6:00 AM the following morning for cold planing and resurfacing activities. Estimated completion date is July 2010. 
 
ROANE COUNTY, I-40 East between Mile Markers 358 and 360: On Wednesday night, May 19, 2010 and Thursday night, May 20, 2010 between the hours of 8PM and 6AM the following morning, motorists should be alert for possible lane closures through this area as crews install median cable barrier. Motorists should be alert for workers present and use extreme caution through this area.
 
ROANE COUNTY, I-40 West between Mile Markers 361 and 364: On Sunday night, May 23, 2010 and Monday night, May 24, 2010 between the hours of 8PM and 6AM the following morning, motorists should be alert for possible lane closures through this area as crews install median cable barrier. Motorists should be alert for workers present and use extreme caution through this area.
 
KNOX COUNTY, I-40 East and West between Rutledge Pike (Exit 392) and the Holston River Bridge (MM 395):Motorists should be alert for lane closures in both directions on Sunday nights through Thursday nights between the hours of 7 p.m. and 6 a.m. as crews resurface the roadway in this area. Motorists should be alert for workers present, expect potential delays, and use extreme caution through this area.
 
 
I-140
 
KNOX COUNTY, I-140 East at Mile Marker 5.00 near Northshore Drive Exit: On Tuesday night, May 25, 2010 between the hours of 8PM and 6AM the following morning, motorists should be alert for possible lane closures through this area as crews install median cable barrier. Motorists should be alert for workers present and use extreme caution through this area.
 
 
I-240
 
REGION IV Maintenance
       Wednesday May 19 through Wednesday May 26, 8AM-4PM, There will be possible lane closures at various locations in Region IV in order to patch potholes on an as needed basis.
       Monday May 24 through Wednesday May 26, 9AM-3PM, There will possible lane closures at various locations in Region IV in order to fix washed out areas.
 
 
I-440
 
REGION 3 On-Call Guardrail:Thursday May 20 through Tuesday May 25, 8PM-6AM, (each night), There will be one lane closures at various locations on interstate routes in Davidson County for guardrail repair and installation.
 
TDOT Maintenance:
       Davidson County
o    Thursday May 20 through Wednesday May 26, 9AM-3PM, There will be possible lane closures at various locations in Davidson County in order to patch potholes on an as needed basis.
o    Thursday May 20 through Wednesday May 26, 9AM-3PM, There will be mobile operations in various locations in Davidson County for vegetation control. This will affect the shoulders or outside lanes. 
 
DAVIDSON COUNTY, I-440 Concrete Rehabilitation:(Recovery Act Project) Thursday May 20 through Wednesday May 26, 8PM-6AM, There will be alternating lane and ramp closures on I-440 eastbound and westbound in order to seal the joints and install permanent striping.
 
DAVIDSON WILLIAMSON COUNTY, ITS Phase III:
       Thursday May 20 through Wednesday May 26, 9AM-3PM and 7PM-6AM, There will be periodic day and night time shoulder closures at various locations within the areas listed below in order to install devices, perform electrical work, and pole installation.
       I-440, both directions, between Hillsboro Pike and I-24 (MM 3 to MM 7)
 
 
I-640
 
No construction activity to report at this time.
 
 
I-55
 
REGION IV Maintenance
       Wednesday May 19 through Wednesday May 26, 8AM-4PM, There will be possible lane closures at various locations in Region IV in order to patch potholes on an as needed basis.
       Monday May 24 through Wednesday May 26, 9AM-3PM, There will possible lane closures at various locations in Region IV in order to fix washed out areas.
 
SHELBY COUNTY, I-55 at Mallory Avenue: I-55 is reduced to two lanes in each direction.  Currently there is no access to Mallory Avenue (Exit 9) from Northbound I-55. Motorists should use the Third Street Exit (Exit 7) and detour to Mallory. Riverside Drive from Mallory Avenue to Devant Street is closed. Motorists should use the newly constructed Riverport Road extension as an alternate route.
       Wednesday May 19 through Wednesday May 26, 9AM-3PM, There will be intermittent lane closures northbound (MM 8 to MM 9) in order to perform bridge construction (Bridge 1, Mallory Ave. overpass). One northbound lane will remain open.
       Saturday May 22 & Sunday May 23, 6AM-12PM,  StartingSaturday there will be a rolling roadblock to repair potholes in both lanes of NB I-55 from 6:00 A.M. till 9:00 A.M. and the inside lane of SB I-55 from 9:00AM. till 12:00PM. This work will be done with time restraints of 15 to 20 minute intervals. If work cannot be done due to weather it will be rescheduled for Sunday.
 
REGION IV On-Call Guardrail
Thursday May 20 and Friday May 21, 8PM-6AM, There will be night time lane closures at the following locations to repair damaged guardrail and cable rail.
       I-55, Shelby County, southbound MM 6.0 to Exit 5B/Elvis Presley Blvd.), 3 lanes to remain open.
       I-55, Shelby County, southbound (MM 5.5 to MM 5.0), 2 lanes to remain open.
       I-55, Shelby County, northbound MM 6.0 to Exit 6A/I-55 NB ramp to I-240 EB, 1 lane to remain open.
 
 
I-155
 
REGION IV Maintenance
       Wednesday May 19 through Wednesday May 26, 8AM-4PM, There will be possible lane closures at various locations in Region IV in order to patch potholes on an as needed basis.
       Monday May 24 through Wednesday May 26, 9AM-3PM, There will possible lane closures at various locations in Region IV in order to fix washed out areas.
 
DYER COUNTY, I-155 Bridge Repair: Wednesday May 19 through Wednesday May 26, 7AM-7AM, Beginning at MM 9 in Missouri and extending to MM 1 in Tennessee.  There will be one eastbound & one westbound lane closed. This work is for the re-painting of the steel structure and for concrete repairs and is a 24 hour closure.
 
DYER COUNTY Resurfacing and Bridge Deck Repairs on I-155 near the rest area LM-9.00 to US-51(SR-3) LM-15.93
       Wednesday May 19 through Wednesday May 26, 7AM-7PM, Beginning at LM-9.00 and extending to LM-15.93. There will be one eastbound & one westbound lane closed. This work is for milling, resurfacing and traffic counter installation on I-155.
       Wednesday May 19 through Wednesday May 26, 7AM-7PM, Beginning at LM-0.00 and extending to LM-1.00. There will be one eastbound & one westbound lane closed. This work is for milling, resurfacing and traffic counter installation on I-155.
       LOOK AHEAD:  Starting Friday, June 04, 2010 at 7:00 PM through Monday, June 7, 2010 at 5:00 AM the interchange of I-155/U.S. 51 and U.S. 412/S.R. 3 ramp will be closed for bridge repair work.  There will be a detour on state routes delineated using changeable message units.  If this work is not completed in one weekend, the work will resume on Friday, June 11, 2010 at 7:00 PM and complete on Monday, June 14 at 5:00 AM.
 
 
I-65
 
REGION 3 Installation of Cable Barrier:
       Thursday May 20 through Wednesday May 26, 8PM-6AM, There will be one lane closed on I-65 northbound and southbound
o    MM 0-2 and 14-19 in Giles County
o    MM 53-61 in Williamson County
o    MM 45-48 in Maury County
o    One lane will remain open.
 
REGION 3 On-Call Guardrail:Thursday May 20 through Tuesday May 25, 8PM-6AM, (each night), There will be one lane closures at various locations on interstate routes in Davidson County for guardrail repair and installation.
 
TDOT Utilities: Sunday May 23, 6AM-4PM, On I-40 & I-65, 300' south of Jo Johnson Ave. overpass near MM 209 in Davidson County. This request by Nashville Electric Service for transferring transmission lines and pulling conductor strands over the interstate. Four rolling stop blocks are expected. Six police cars will be present.
 
TDOT Maintenance:
       Davidson County
o    Thursday May 20 through Wednesday May 26, 9AM-3PM, There will be possible lane closures at various locations in Davidson County in order to patch potholes on an as needed basis.
o    Thursday May 20 through Wednesday May 26, 9AM-3PM, There will be mobile operations in various locations in Davidson County for vegetation control. This will affect the shoulders or outside lanes. 
o    Saturday May 22 and Sunday May 23, 6AM-2PM There will be rolling roadblocks in the left lane at the following locations in Davidson County for cleaning grates and removing vegetation:
§ I-65 southbound from mile marker 81 to mile marker 74
 
DAVIDSON and WILLIAMSON COUNTIES, ITS Phase III:
       Thursday May 20 through Wednesday May 26, 9AM-3PM and 7PM-6AM, There will be periodic day and night time shoulder closures at various locations within the areas listed below in order to install devices, perform electrical work, and pole installation.
       I-65, both directions, between Concord Rd and Long Hollow Pkwy (MM 70 to MM 97)
 
DAVIDSON COUNTY, I-65 at the junction with SR 12 (Rosa Parks Blvd.)
       Thursday May 20 through Wednesday May 26, 9PM-5AM, There will be alternating lane closures on Rosa Parks Blvd. for utility work. One lane will remain open in each direction.
       Saturday May 22 and Sunday May 23, 5AM-9PM, There will be alternating lane closures on Rosa Parks Blvd. for utility work. One lane will remain open in each direction.
 
SUMNER COUNTY, Bridge repair of two bridges on I-65 over U.S. 31W & on US 31W over US 41:Friday May 21, 8PM through Monday May 24, 6AM, There will be one lane on I-65 southbound and northbound closed in order to seal the bridge deck. One lane will remain open in each direction. Also, the I-65 northbound exit ramp to SR 41 westbound will be closed in order to paint the bridge.
 
 
I-69
 
Obion County-Future I-69 beginning 0.31 mile south of SR-5/SR-22 to 0.78 mile west of SR-21:CLOSED thru November 3, 2011, Brevard Road, George Moss Road and Mt. Zion Road is closed to through traffic. Detour signs will be posted to guide drivers around the construction area.
 
 
I-75
 
HAMILTON, BRADLEY, and MARION COUNTIES, I-75 / I-24 / SR-153 / SR-29 construction of an intelligent transportation system on various interstate and state routes in and near Chattanooga: The contractor will implement shoulder closures throughout this report period within the project area on weekdays between the hours of 9:00 AM and 4:00 PM and anytime on the weekend as part of the ITS construction. On weekdays during non-peak hours, the contractor will have a right lane closure on SR-29 South at MM 2.5. Three lanes are to remain open with third available lane used as acceleration lane for on-ramp from Manufacturers Road. There also may be weeknight lane closures throughout the project between the hours of 10:00 PM and 5:00 AM, nighttime weekend lane closures between the hours of 10:00 PM and 10:00 AM, and intermittent temporary stoppages of traffic (less than 15 minutes) at various locations throughout the project area to allow the contractor to perform ITS work. THP will assist with traffic control. Estimated completion date is December 2010. 
 
HAMILTON COUNTY, I-75 widening project from 1.1 miles south of Lee Highway (SR-2, US-11) to 1.2 miles north of Lee Highway (SR-2, SR-11): The contractor will have a lane closure on I-75 North and South between the hours of 10:00 PM and 6:00 AM to accommodate new concrete paving operations. One lane of traffic will remain open at all times.  The contractor will have lane closures on Hill Top Road, Hunter Road, Snow Hill Road, Mountain View Road, Lee Highway, and Old Lee Highway from 8:30 AM until 7:00 PM to construct new roadway and accommodate bridge construction. However, the contractor must move off the roadway from 2:30 PM until 3:00 PM each day during the shift change at Miller Industries. One lane will remain open at all times. Estimated completion date is December 2010. 
 
MCMINN COUNTY, I-75 resurfacing from north of MM 39 (LM 4) to the rest area at MM 45 (LM 10): This is a nighttime paving project that will take place on I-75 North and South on Sundays through Thursdays between the hours of 7:00 PM to 6:00 AM. One lane will remain open to traffic at all times. Estimated completion date is June 2010. 
 
ANDERSON COUNTY, I-75 North near Mile Marker 121.5: On Sunday night, May 23, 2010 motorists should be alert for a left lane closure through this area between 8 p.m. and 6 a.m. the following morning as crews perform median cable barrier repairs. Motorists should be alert for workers present, use extreme caution and expect potential delays traveling through this area.
 
ANDERSON COUNTY, I-75 North and South between Mile Markers 127 and 129:On Sunday night, May 23, 2010 through Tuesday night, May 23, 2010 motorists should be alert for possible lane closures through this area between 8 p.m. and 6 a.m. the following morning as crews install median cable barrier. Motorists should be alert for workers present, use extreme caution and expect potential delays traveling through this area.
 
ANDERSON COUNTY, I-75 South between Exit 128 (Lake City) and Mile Marker 127: Motorists should be alert for workers present, equipment entering and exiting the roadway and use extreme caution through this noise wall construction project. 
 
CAMPBELL COUNTY, I-75 South near Mile Marker 152.3: On Sunday night, May 23, 2010 motorists should be alert for a left lane closure through this area between 8 p.m. and 6 a.m. the following morning as crews perform guardrail repairs. Motorists should be alert for workers present, use extreme caution and expect potential delays traveling through this area.
 
CAMPBELL COUNTY, I-75 North near Mile Marker 155.9: On Sunday night, May 23, 2010 motorists should be alert for a left lane closure through this area between 8 p.m. and 6 a.m. the following morning as crews perform guardrail repairs. Motorists should be alert for workers present, use extreme caution and expect potential delays traveling through this area.
 
 
I-275
 
No construction activity to report at this time.
 
 
I-81
 
SULLIVAN COUNTY, I-81 North and South between Exit 69 and Exit 74:Motorists should be alert for lane closures on Sunday nights through Thursday nights between the hours of 7 p.m. to 6 a.m. the following morning as crews mill and resurface the roadway. Motorists should be alert for workers and equipment present and use extreme caution traveling through this area.
 
SULLIVAN COUNTY, I-81 North and South between Mile Markers 57 and 63:Motorists should be alert for lane closures on Sunday nights through Thursday nights between the hours of 7 p.m. to 6 a.m. the following morning as crews mill and resurface the roadway. Motorists should be alert for workers and equipment present and use extreme caution traveling through this area.
 
 
Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity.
 
Most work is weather dependent and subject to change due to inclement weather.
 
TDOT is now on Twitter: 
       For statewide: www.twitter.com/TN511
       For Knoxville, the Tri-Cities, and Upper East Tennessee: www.twitter.com/knoxville511.
       For Chattanooga, Cookeville, Crossville, and the Cumberland Plateau: www.twitter.com/chattanooga511
       For Nashville, Clarksville, Murfreesboro, and Middle Tennessee: www.twitter.com/nashville511
       For Memphis, Jackson, and West Tennessee: www.twitter.com/memphis511

Motorists are reminded to use all motorist information tools responsibly. Drivers should refrain from texting, tweeting, or using a mobile phone while operating a vehicle. TDOT advises drivers to "Know before you go!" by checking traffic conditions before leaving for your destination. 

Press Releases | Road Closures