CARROLL COUNTY, SR-436  State Route 436 between State Route 77 (US 70A) (Reedy Creek Rd.) and State Route 76 (S. Highland Dr.) is CLOSED for a bridge replacement project. A detour route is posted
Wednesday September 1 through Wednesday September 8, State Route 436 between State Route 77 (US 70A) (Reedy Creek Rd.) and State Route 76 (S. Highland Dr.) is CLOSED for a bridge replacement project. A detour route is posted.
 
CARROLL COUNTY, SR1 (US70) Bridge rehabilitation and repair at log mile 11.02, 13.08, and 14.43 will result in lane closures each day. Traffic will be controlled by a temporary traffic signal.
 
DECATUR COUNTY, US 412 (SR 20) Widening Project:  Motorists should be alert for temporary lane closures each day along US412 (State Route 20) from near the Henderson County line to Bear Creek Rd. as crews work to widen the road.
Wednesday September 1 & Thursday September 2, 6:30 a.m.-6:00 p.m.: There will be temporary lane closures each day for excavation, with flagmen present. Watch for haul trucks entering roadway. One lane traffic with flagmen.
Friday September 3, 6:30 a.m.-12:00 p.m.: There will be temporary lane closures each day for excavation, with flagmen present. Watch for haul trucks entering roadway. One lane traffic with flagmen
 
DYER COUNTY, I-155 Bridge Repair:  
Wednesday September 1 & Thursday September 2: Beginning at Mile Marker 9 in Missouri and extending to Mile Marker 1 in Tennessee.  There will be one eastbound & one westbound lane closed. This work is for the re-painting of the steel structure and for concrete repairs and is a 24 hour closure.
Friday September 3, 7:00 a.m.-12:00 p.m.: Beginning at Mile Marker 9 in Missouri and extending to Mile Marker 1 in Tennessee.  There will be one eastbound & one westbound lane closed. This work is for the re-painting of the steel structure and for concrete repairs.
 
FAYETTE COUNTY-Re-Surfacing on I-40 Eastbound MM 27 through MM 35
Tuesday September 7 through Friday September 10, 7:00 p.m.-6:00 a.m.: There will be one lane closed on I-40 eastbound, Mile Marker 27.0-Mile Marker 35.0, for paving operations. Tennessee Highway Patrol will assist with traffic control.
 
GIBSON COUNTY, SR-425:  Grade, drain and paving operations beginning west of Gann Road to Salem Street.
 
GIBSON COUNTY, SR-76: (Recovery Act Project) A widening project from State Route 43 to the Carroll County line will result in temporary lane closures each day. Motorists are advised to travel with caution.
Wednesday September 1 & Thursday September 2, 6:00 a.m.-6:00 p.m.:  There will be brief lane closures throughout the project for utility work (power lines, new service lines, etc). Motorist should use caution and watch for heavy equipment entering and leaving roadway.
Wednesday September 1 & Thursday September 2, 7:00 p.m.-6:00 a.m.,  There will be brief lane closures at the intersection of US-45 and US-79, for utility work (storm sewer pipe). Motorist should use caution and watch for heavy equipment entering and leaving roadway.
Friday September 3, 6:00 a.m.-12:00 p.m.: There will be brief lane closures throughout the project for utility work (power lines, new service lines, etc). Motorist should use caution and watch for heavy equipment entering and leaving roadway.
 
HARDEMAN COUNTY SR57: Construction of 3 bridges over Big Muddy Creek at log mile 20.38, 20.29, and 20.64. Bridge replacement construction will result in narrowed lanes daily.
 
HARDIN COUNTY, SR-15: construction of 4-lane highway from near Savannah to Firetower Road. Motorists should use caution and watch for construction equipment entering and leaving roadway in this area.
Wednesday September 1 & Thursday September 2, 6:00 a.m.-6:00 p.m.: There will be some flagging due to heavy equipment hauling rip-rap, road and drainage. Maintaining erosion control measures, clearing, grading, milling, paving and under drain operation will be ongoing.
Friday September 3, 6:00 a.m.-12:00 p.m.: There will be some flagging due to heavy equipment hauling rip-rap, road and drainage. Maintaining erosion control measures, clearing, grading, milling, paving and under drain operation will be ongoing.
 
HAYWOOD COUNTY, SR-1 (US70): Bridge repair on 4 bridges will result in lane closures each day over Overflow at Log Mile 5.58, Log Mile 5.92, Log Mile 6.27 and over Muddy Creek at Log Mile 6.37. Traffic will be controlled by a temporary traffic signal with a width restriction of 11'3".
 
HAYWOOD COUNTY, SR-1 (US70): Bridge repair will result in lane closures each day on 6 bridges over Overflow Hatchie River at Log Mile 7.23, 7.65, 8.15, 8.40, 8.84 and 9.10. Traffic will be controlled by a temporary traffic signal.  The roadway is reduced to one 11'3” with a temporary signal.
 
HAYWOOD COUNTY, SR-1 (US70): A bridge rehabilitation at log mile 25.74 and a bridge repair a log mile 26.62 will cause daily temporary lane closures.
 
HAYWOOD COUNTY, SR-76 Bridge Replacement: A bridge replacement project will result in lane closures each day. Traffic will be controlled by a temporary traffic signal.
 
HENDERSON COUNTY Design-Build on SR-104 over I-40 MM 101.00 
Wednesday September 1 through Wednesday September 8: THERE ARE NO SCHEDULED CLOSURES.
 
HENDERSON COUNTY-Resurfacing on I-40 between Mile Marker 115 and 121
Tuesday September 7 through Friday September 10, 7:00 p.m.-6:00 a.m.: There will be one lane closed on I-40 eastbound and westbound, for paving operations.
 
HENDERSON COUNTY, SR-20: construction of 4-lane highway from Madison County line to west of Crucifer Road. Watch for construction equipment entering and leaving roadway.
Wednesday September 1 through Wednesday September 8, There are no scheduled closures.
 
HENRY COUNTY, SR-54 Widening: A widening project to add a turn lane to State Route 218 will result in intermittent lane closures on weekdays.
 
LAKE COUNTY, SR-21 Bridge Construction: Construction of a bridge over the Reelfoot Spillway. Traffic is being shifted to a run-around that will be in place for the duration of the project.
 
MADISON COUNTY, US 412 (SR 20) Widening: Widening project between Interstate 40 and Miller Avenue will temporarily slow traffic each day. Motorists are advised to use caution when traveling through this work zone. Drivers should be alert for trucks and equipment entering and leaving the roadway.
NOW through Monday September 20, 2010, Hollywood Drive traffic has been shifted on a temporary run-around over Old Hickory Creek in order to begin bridge construction. Both the North and South Bound lanes of traffic are reduced to 30 miles per hour as plans designed. Demolition work on the bridge has begun.
 
McNAIRY COUNTY, US 64 (SR 15): (Recovery Act Project) Widening project between State Route 225 and Sandy Flat Road will result in traffic shifts. Motorists are advised to use caution when traveling through this work zone. Be alert for trucks and equipment entering and leaving the roadway.
Wednesday September 1 & Thursday September 2, 6:00 a.m.-6:00 p.m.: There will be some flagging due to heavy equipment hauling select material rip-rap, road and drainage. There is also on going bridge construction and concrete trucks entering from Highway 64.
Friday September 3, 6:00 a.m.-12:00 p.m.: There will be some flagging due to heavy equipment hauling select material rip-rap, road and drainage. There is also on going bridge construction and concrete trucks entering from Highway 64.
 
OBION COUNTY-Future I-69 beginning 0.31 mile south of SR-5/SR-22 to 0.78 mile west of SR-21
NOW through Thursday November 3, 2011, Brevard Road near Goodyear in Union City will be CLOSED for the construction of an interchange at this location so that Brevard Road will cross over I-69. A detour route is posted.
NOW through Saturday September 15, 2012, Perry Browder Road between George Moss Road and Mt. Zion Road will be CLOSED for the construction of an interchange at this location. A detour route is posted. There is only one house on this section of Perry Browder Road and they will provide egress and ingress daily as the project is constructed.
 
OBION COUNTY, SR-5: bridge replacement, over Cane Creek Log Mile - 22.37 and over North Fork Hoosier Creek Log Mile -18.22.  Roadway reduced to one (11’) lane Northbound with a temporary signal.
 
REGION IV Maintenance
Wednesday September 1 through Wednesday September 8, 9:00 a.m.-3:00 p.m.: There will possible lane closures at various locations in Region IV in order to fix washed out areas.
 
REGION IV On-Call Guardrail
Wednesday September 1 through Friday September 3, 8:00 p.m.-6:00 a.m.: There will be night time lane closures at the following locations to repair damaged guardrail and cable rail.
 
I-40, Shelby County, eastbound (Mile Marker 23.0 to Mile Marker 23.5), one lane to remain open.
I-40, Shelby County, westbound (Mile Marker 12.0 to Mile Marker 11.5), two lanes to remain open.
I-40, Shelby County, westbound (Mile Marker 10.5 to Mile Marker 10.0), two lanes to remain open.
I-40, Shelby County, westbound (Mile Marker 8.5 to Mile Marker 7.2), two lanes to remain open.
I-240, Shelby County, westbound Exit 17, one ramp lane to remain open.
 
REGION IV On-Call Pavement Markings
Tuesday September 7 & Wednesday September 8, 8:00 p.m.-6:00 a.m.: There will be night time lane closures at the following location for restriping operations.   Tennessee Highway Patrol will assist with traffic control.
 
I-240, Shelby County, eastbound Exit 12C, one lane to remain open.
 
SHELBY COUNTY, SR-1 (US70) @ Canada Road : Intersection improvements (grading, draining, paving, signing, striping, and signalization) will result in daily lane closures in both directions. Motorists are reminded to use caution when driving through this intersection.
 
SHELBY COUNTY, Seismic Retrofit on the bridge on I-40 over the Mississippi River
Various closures for existing six lane cross-section (arch spans and westward):
Wednesday September 1, 12:00 a.m. through Friday September 3, 12:00 p.m.: There will be one eastbound and one westbound lane closed.
Tuesday September 7, 9:00 a.m.-5:00 p.m.: There will be two eastbound and one westbound lane closed.
Tuesday September 7, 5:00 p.m. through Wednesday September 8: There will be one eastbound and one westbound lane closed.
 
Various closures for existing four lane section (east of the arch spans):
Wednesday September 1, 12:00 a.m. through 6:00 a.m.: There will be one eastbound and one westbound lane closed.
Wednesday September 1, 7:00 p.m. through Thursday September 2, 6:00 a.m.: There will be one eastbound and one westbound lane closed.
Thursday September 2, 7:00 p.m. through Friday September 3, 6:00 a.m.: There will be one eastbound and one westbound lane closed.
Tuesday September 7, 9:00 a.m. through Wednesday September 8: There will be one eastbound and one westbound lane closed.
 
Beginning at 9AM on Tuesday September 07, I-40 will be reduced to one eastbound and one westbound lane for traffic for about 71 days.
 
SHELBY COUNTY, Grade, Drain & Paving on SIA Route serving the B. N. S. F. Railway
Wednesday September 1 through Wednesday September 8: No Closures Scheduled.
 
SHELBY COUNTY, SR-3 (US-51/Thomas Street) at Wolf River: Bridge construction. 
Wednesday September 1 through Wednesday September 8, Roadway reduced from 4 lanes to one (11’) lane in each direction.
 
SHELBY COUNTY, SR57 (US72): This is a bridge rehabilitation on State Route 57 (Poplar Avenue) over the westbound ramp to I-240 at log mile 8.8
 
SHELBY COUNTY, SR-385:Between SR57 and SR193, grading, drainage, and bridge construction of State Route 385 from State Route 57 Poplar Ave. in Piperton to State Route 193 Macon Rd. in Fisherville. The contractor is currently driving piles, constructing bridge caps, foundations, and columns, and hauling embankment. Trucks will be entering the highway at State Route 205 in the vicinity of the Wolf River and overflow bridges. Construction work will temporarily slow traffic every day.
 
SHELBY COUNTY, I-55 at Mallory Avenue: I-55 is reduced to two lanes in each direction. Currently there is no access to Mallory Avenue (Exit 9) from Northbound I-55. Motorists should use the Third Street Exit (Exit 7) and detour to Mallory. Riverside Drive from Mallory Avenue to Devant Street is closed. Motorists should use the newly constructed Riverport Road extension as an alternate route.
Wednesday September 1 & Thursday September 2, 9:00 a.m.-3:00 p.m.: There will be intermittent lane closures northbound (MM 8 to MM 9) in order to perform bridge construction between Bridges 1 & 2. One northbound lane will remain open.
Friday September 3, 6:00 a.m.-12:00 p.m.: There will be intermittent lane closures northbound (MM 8 to MM 9) in order to perform bridge construction between Bridges 1 & 2. One northbound lane will remain open.
 
TIPTON COUNTY, SR-14 (Austin Peay Highway): (Recovery Act Project)grade, drain and paving operations, beginning north of SR-206 and extending to 1.2 miles east of SR-384.
Wednesday August 25 through Wednesday September 1, There are no scheduled closures.
 
TIPTON COUNTY, SR-59:(Recovery Act Project) bridge replacement, over drainage ditch of Little Beaver Creek Log Mile - 24.54.
 
For more information on TDOT road construction projects or to view travel conditions visit the TDOT SmartWay Information System web site (http://www.tn.gov/tdot/tdotsmartway/). Motorists can also dial 511 from any land-line or cellular phone to access up to date traffic conditions. TDOT is also now on Twitter. For up to date traffic tweets for the Jackson & Memphis areas follow Memphis511 (http://twitter.com/memphis511). For statewide traffic information follow TN511 (http://twitter.com/TN511). 
 
Motorists are reminded to use all motorist information tools responsibly. Drivers should refrain from texting, tweeting or using a mobile phone while operating a vehicle. TDOT advises drivers to “Know before you go!” by checking traffic conditions before leaving for your destination.
 
All scheduled work is subject to change due to adverse weather conditions or other conditions beyond the control of the contractor.
 
###
For More Information Contact:
Nichole Lawrence
731.935.0318 
 