Middle Tennessee Construction January 2nd-8th, 2014

Thursday, January 02, 2014 | 03:23am

Middle Tennessee Construction

January 2nd-8th, 2014

DAVIDSON COUNTY, Widening of I-65 from Trinity Lane to Dickerson Rd.

  • Monday January 6 and Wednesday January 8, 12 Noon-3PM, There will be rolling roadblocks on I-65 southbound between the I-24 ramp and Trinity Lane for blasting.  Troopers will be utilized.

DAVIDSON COUNTY, Bridge Construction on Gallatin Rd. over the CSX Railroad

  • From now through April 2014, Gallatin Rd. will be reduced to one lane in each direction in this area.
  • Monday January 6 through Wednesday January 8, 9PM-5AM, There will be alternating lane closures on Gallatin Rd. in order to install conduit across the road.

DAVIDSON COUNTY, Bridge Repair on I-40 over Jefferson St. and the Nashville & Western Railroad, including the Pedestrian Bridge over I-40

  • Thursday December 19 through Monday December 23, 7AM-7PM, There will be alternating lane closures on Jefferson St. under I-40 in order to paint the bridge.

DAVIDSON COUNTY, Misc. Safety Improvements 21st Ave at Children’s Way

  • Thursday January 2 through Wednesday January 8, 8PM-5AM, There will be alternating lane closures on Children’s Way and Capers Ave in order to shift traffic for the installation of a new traffic signal.

DAVIDSON COUNTY, Ramp Repair on SR 45 (Old Hickory Blvd) on ramp to I-40 W near Summit Hospital

  • Friday January 3 at 8PM through Monday January 6 at 6AM, Old Hickory Boulevard southbound ramp to I-40 will be closed for ramp repair.  

Performance Based Maintenance Work on I-24, I-65 and SR 840

  • Thursday January 2 through Wednesday January 8, 9AM-3PM, There will be possible lane closures at the following locations on State Routes and Interstates in Middle Tennessee to patch potholes on an as needed basis:
    • SR 840, Williamson, Rutherford and Wilson
    • I-24, Rutherford and Bedford
    • I-65, Williamson
  • Thursday January 2 through Wednesday January 8, 8PM-5AM, There will be possible lane closures at the following locations on State Routes and Interstates in Middle Tennessee to repair guardrail on an as needed basis:
    • SR 840, Williamson, Rutherford and Wilson
    • I-24, Rutherford and Bedford
    • I-65, Williamson

DAVIDSON AND SUMNER COUNTIES, Installation of Smartway ITS Message Signs

  • Friday January 3 through Wednesday January 8, 9PM-5AM, There will be a lane closure on I-40 WB MM 204 (Briley Pkwy/ White Bridge Rd.) for installation of camera pole.
  • Friday January 3 through Wednesday January 8, 7AM-3PM, There will be a shoulder closure on I-40 WB MM 204 on the right shoulder to install conduit by DMS sign.
  • Friday January 3 through Wednesday January 8, 7AM-3PM, There will be a shoulder closure on I-24 WB MM 42.2 on left and right sides for DMS foundation and conduit installation.
  • Friday January 3 through Wednesday January 8, 7AM-3PM, There will be a shoulder closure on SR 386 near Conference Dr. eastbound on ramp for DMS foundation and conduit installation.

DICKSON COUNTY, ON CALL CONCRETE REPAIR

  • Thursday January 2 through Wednesday January 8, 9AM-3PM, Lanes will be shifted on I-40 EB at mile 172 on ramp in Dickson County for concrete repair.

WILSON COUNTY, I-40 Widening from Central Pike to East of SR 109

  • No lane closures this week

WILLIAMSON COUNTY, Widening of I-65 from SR 840 to SR 248, Interchange Modifications and Widening on SR 248 from Lewisburg Pike to west of I-65

  • Monday January 6 through Wednesday January 8, 1PM, There will be rolling roadblocks on I-65 northbound and southbound near MM 62.0 and on SR 248 eastbound and westbound at the interchange in order to blast in the median.  Uniformed officers will be utilized.

WILLIAMSON COUNTY, Construction on SR 397 (Mack Hatcher Pkwy) South of SR 96 to SR 6

  • No lane closures this week

WILLIAMSON COUNTY, Widening of SR 253 (Concord Rd.) from Sunset Rd. to Nolensville Rd.

  • Thursday January 2 through Wednesday January 8, 9AM-3PM, Traffic will be flagged during trench and boring operations.

 

TDOT Maintenance:

Middle Tennessee

  • Thursday, January 2 through Wednesday, January 8, 9AM-3PM, (excluding weekends), There will be possible lane closures at various locations on State Routes and Interstates in Middle Tennessee to patch potholes on an as needed basis:
  • I-24 Cheatham, Davidson, Montgomery and Robertson Counties
  • I-65 Davidson, Robertson, Williamson Counties
  • I-40 Cheatham, Davidson, Dickson, Hickman, Humphreys Counties

DAVIDSON COUNTY

  • Thursday, January 2 through Wednesday, January 8, 9AM-3PM and 8PM-5AM, There will be mobile operations in various locations on the interstates in Davidson County for Drain Cleaning Operations.  This will affect the shoulders or inside and outside lanes.

 

Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity.  Information in this report is provided to the Department of Transportation by the contractors.  Most work is weather dependent and subject to change due to inclement weather.  For travel information visit the TDOT SmartWay web site at www.tn.gov/tdot/tdotsmartway or call 5‑1‑1.  You can also receive traffic alerts via TDOT’s multiple Twitter feeds, including statewide traffic tweets @TN511 or Nashville area alerts @Nashville511

Android and iPhone users can download TDOT’s SmartWay Mobile App to assist them in navigating Tennessee highways.  The app provides up-to-the-minute customized traffic information and enables the user to access TDOT’s SmartWay cameras, messages displayed on overhead Dynamic Message Signs, and information on construction related lane closures and incidents on interstates and state routes.  The TDOT SmartWay App is free and available for download in the Apple App Store and Play Store for Android. 

As always, drivers are reminded to use all motorist information tools wisely and Know Before You Go! by checking travel conditions before leaving for their destination.  Drivers should never tweet, text or talk on a cell phone while behind the wheel.

 

For More Information Contact:

Deanna Lambert, TDOT Community Relations Officer

Deanna.Lambert@tn.gov

(615) 854-5650 cell 

###