Weekly Roadway Activity Report for TDOT Region 2 (May 09 - 15, 2019)

Thursday, May 09, 2019 | 01:30pm

DISTRICT 27

CUMBERLAND COUNTY I-40 Resurfacing from near the parking area (MM 306.34) to east of Exit 311 (MM 311.12):   Construction signs have been installed. The contractor is scheduled to pave eastbound and westbound which will require night time lane closures. State trooper assistance will be requested. Working hours will be from 7 PM to 6 AM. During working hours, the speed limit will be reduced from 70 mph to 60 mph using digital speed limit sign assemblies.  Estimated project completion date is August 2019.

[Rogers Group, Inc./Bradley/CNS325]

CUMBERLAND COUNTY SR-101 (Peavine Road) Grading, drainage, and paving from Firetower Road to Westchester/Catoosa Boulevard: As grade work progresses, motorists should be alert for shifts in traffic patterns to allow for construction activities. The posted speed limit has been reduced from 45 mph to 35 mph within the work zone. Temporary lane closures and traffic stoppages may be needed to support ongoing work. Lane and/or road closures will be needed within Fairfield Glade to allow installation of storm drain and relocation of utilities. If needed, alternate routes will be coordinated with the Glade and properly identified. Motorists should reduce speeds on Peavine Road and be alert for construction personnel/equipment entering and exiting the roadway.  Estimated project completion date is November 2020.

[Rogers Group, Inc./Bradley/CNQ921]

FENTRESS COUNTY Rotten Fork Road over Rotten Fork of the Wolf River Bridge Replacement: Work on this site has been temporarily suspended until further notice to contractor. Existing roadway will remain open during the course of construction, but motorists are encouraged to use caution around construction site due to close proximity of construction equipment. Estimated project completion date is November 2019.

[Twin K Construction/Moore/CNT901]

FENTRESS COUNTY SR-52, SR-154 and SR-297 Resurfacing (microsurfacing): The contractor has re-scheduled their work to begin 05/18/19. No work is currently ongoing on this contract. The routes covered in the project are SR-52 from east of US-127 (SR-28) (LM 13.60) to SR-296 (LM 17.62), SR-154 from north of Louvaine Road (LM 6.25) to the Pickett County line (LM 13.48), and SR-297 from SR-154 (LM 0.00) to the Scott County line (LM 8.79).  Estimated project completion date is June 2019.

[Hudson Construction Company/Moore/CNS098]

FENTRESS COUNTY Vines Ridge Road over Big Laurel Creek Bridge Replacement: Vines Ridge Road remains closed at LM 1.06 and will remain closed until the new bridge is constructed and in place. Approximate date for the length of closure is 07/31/19. Motorists should seek alternate route around Vines Ridge Road near location of construction. Estimated project completion date is November 2019.

[Twin K Construction/Moore/CNT901]

FENTRESS AND OVERTON COUNTY SR-85 Emergency slide repairs at various locations: The roadway is closed from LM 18.4 to LM 22.4 in Overton county. SR-85 is also closed in Fentress County between LM 5.75 and 8.00. The contractor is continuing work on this contract in the two areas listed where the roadway is closed. Motorists are encouraged to use caution and seek alternate routes. Estimated project completion date is November 2019.

[Wright Brothers Construction Company, Inc./Moore/CNT154]

PUTNAM COUNTY I-40 near MM 296 Bridge repair on Rocky Point Road over I-40: Rocky Point Road bridge at LM 10.08 over I-40 will be closed due to bridge repairs and is scheduled to re-open in June 2019. A detour is in place to guide motorists around the bridge closure. The contractor will be performing lane closures on I-40 from MM 295 to MM 298 during this period. Lane closures will be performed between the hours of 8 PM and 6 AM in the eastbound and westbound direction. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone.  Estimated project completion date is August 2019.

[Mid-State Construction Company, Inc./Cookeville/CNS355]

PUTNAM COUNTY SR-111 (LM 4.08) at I-40 (MM 288) Signal installation on east and westbound ramps in Cookeville, including grading, drainage and paving: The contractor will be constructing foundations for the traffic signal poles along SR-111 North and South and along each of the I-40 ramps. This will result in temporary shoulder closures each day. The contractor has begun widening the I-40 westbound off-ramp, resulting in a right shoulder closure with barrier rail. Right turns from the westbound off-ramp onto SR-111 North are not allowed while this area is being excavated. This closure will be in place until 06/01/19. Motorists are advised to use an alternate route during this time. If they must travel through this area, they will experience long delays, as the left turn movement will be the only one allowed. Motorists should use caution when traveling through the work zone. Estimated project completion date is June 2019.

[Rogers Group, Inc./Cookeville/CNS279]

PUTNAM COUNTY Utility Work on SR-135 (S. Willow Avenue) in both directions from LM 9 to LM 9.90: Rolling lane & shoulder closures for utility work will take place from Fairgrounds St. to Jackson St. Message boards and cones will be present. Motorists should use caution and be aware of moving personnel and equipment as crew’s transition along Willow Ave. from 05/13/19 through 05/22/19 between 9 AM to 3 PM.

 

PUTNAM COUNTY Utility Work on SR-136 (N. Washington Avenue) in both directions from LM 4.5 to LM 5.4: Utility work between 4th St. & 6th St. Signage, barrels, and cones will be present during this work. Motorists should use caution and be aware of flaggers. Work should continue through 06/18/19 between 9 AM and 3 PM.

 

DISTRICT 28

BLEDSOE COUNTY SR-101 Bridge repair over Bee Creek (LM 8.98): Work on this project is underway. For the safety of the traveling public, the bridge will be reduced to one 10 foot lane and controlled with temporary signals. RESTRICTIONS: 10 foot lane Estimated project completion date is September 2019.

[Jamison Construction, LLC/Voiles/CNS266]

COFFEE COUNTY I-24 Resurfacing from Bedford County (MM 96) to Noah Fork Creek (MM 101) including bridge deck repair: The contractor will continue the milling and paving process of the roadway surface each Sunday thru Thursday during the hours of 7 PM to 6 AM each night. There will be lane closures during all work processes. Motorists should use extreme caution. Law enforcement and safety personnel will be present.  Estimated project completion date is August 2019.

[Rogers Group, Inc./Hussein/CNS332]

COFFEE COUNTY TDOT Maintenance on SR-2 (US-HWY. 41) in both directions at LM 0.51: Region 2 Bridge Repair will be repairing the sidewalk on SR-2 on Monday and Tuesday, 05/13/19 through 05/14/19, from 9 AM to 3 PM.

MARION COUNTY TDOT Maintenance on SR-2 (US-HWY. 41) both directions at LM 25.6: Slide repair work has route reduced to one lane with traffic signals controlling alternating directions.

[TDOT Maintenance/Miner/MAINT]

MARION COUNTY Utility Work on SR-27 (US-HWY. 72) in both directions from LM 4.67 to LM 7.52: A mobile lane closure for electrical work will take place along Hwy 27 between Hwy 41 @ East Valley Rd. Motorists should use caution and be aware of flaggers. Work will take place from 04/23/19 through 07/01/19 between 6 AM and 4 PM.

MARION COUNTY SR-156 over Running Water Creek (LM 25.58) Bridge rehabilitation: SR-156 is reduced to one 10 foot lane across Running Water Creek Bridge and controlled with a temporary traffic signal while the bridge is repaired. Please use caution when traveling through this area. RESTRICTIONS: 10 foot lane Estimated project completion date is October 2019.

[Mid-State Construction Company, INC/Voiles/CNS905]

WARREN COUNTY TDOT Maintenance on SR-136 (ROCK ISLAND RD.) in both directions at LM 1.99: Bridge inspection will be performing its 2-year inspection on the SR-136 bridge over the Caney Fork River at LM 1.99 on Monday, 04/13/19 from 9 AM to 2 PM. Both lanes may have to be closed during the inspection but only one at a time.

WARREN COUNTY TDOT Maintenance on SR-286 (MORRISON ST.) in both directions at LM 0.59: Bridge inspection will be performing its 2-year inspection on the SR-286 bridge over the Hickory Creek at LM 0.59 on Thursday, 04/09/19 from 9 AM to 2 PM. Both lanes may have to be closed during the inspection but only one at a time.

WARREN COUNTY TDOT Maintenance on SR-287 (GREAT FALLS RD.) in both directions at LM 39.48: Bridge inspection will be performing its 2-year inspection on the SR-287 bridge over the Collins River (Great Falls Lake) at LM 39.48 on Tuesday, 04/14/19 from 9 AM to 2 PM. Both lanes may have to be closed during the inspection but only one at a time.

WARREN COUNTY SR-288 Construction of a concrete bulb-tee beam bridge over Collins River (LM 4.97), including grading, drainage and paving: The bridge is currently reduced to one 10.5-foot lane to allow the contractor to construct the new bridge. While the bridge is down to one lane, traffic will be maintained and controlled by a temporary signal. Motorists should expect periodic delays and use caution in the work zone. RESTRICTIONS: 10.5-foot max width Estimated project completion date is September 2019.

[Palmertree Construction Company, LLC/Parnham/CNQ270]

WARREN COUNTY SR-8 over Collins River (LM 8.14) Bridge Repair: The bridge is currently reduced to one 11-ft. lane to allow the contractor to repair the existing bridge. While the bridge is down to one lane, traffic will be maintained and controlled by a temporary signal for the safety of the traveling public. Motorists should expect periodic delays and use caution in the work zone. RESTRICTIONS: 11-ft max width. Estimated project completion date is August 2019.

[Jamison Construction/Parnham/CNS254]

DISTRICT 29

BRADLEY COUNTY US-64BP (US-74, SR-311) Resurfacing from east of Goldstar Drive (LM 3.08) to east of McGrady Drive (LM 5.00), including bridge deck repair: The contractor will have nightly lane closures from 8 PM to 6 AM Monday through Saturday to install snowplowable pavement markers and permanent striping. One lane will be closed on SR-311 while this work occurs.  Estimated project completion date is May 2019.

[Talley Construction Company, Inc./Curtis/CNS238]

BRADLEY AND MCMINN COUNTY SR-306 Miscellaneous safety improvements from SR-60 (LM 0) to the Meigs County line (LM 8.58), and on SR-307 from Burnett Road (LM 2.18) to Old Mount Harmony Road (LM 6.07): The contractor will be working on SR-306 and will be having intermittent lanes closures as they work. Estimated project completion date is July 2019.

[Superior Pavement Markings, Inc./Curtis/CNS341]

BRADLEY AND MCMINN COUNTY SR-312 (Bradley Co.) Miscellaneous safety improvements from the Hamilton Co. Line (LM 0.00) to Quill Dr. (LM 5.27); US-11 (SR-2) (McMinn Co.) miscellaneous safety improvements from Sanford Rd. (LM 4.05) to Chapel Rd. (LM 12.32): Work on this project is underway. The contractor will work in Bradley County on SR-312 during this report period. There will be intermittent lane closures. Flaggers will assist with traffic control. Estimated project completion date is June 2019.

[Superior Traffic Control, LLC/Curtis/CNS287]

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction: Crews will continue surveying and spotting utilities at various locations throughout the interchange. Shoulders may be closed at these locations between 9 AM and 3 PM. The contractor may have temporary nighttime lane closures throughout the project on Sundays through Thursdays between 9PM and 6AM. Additionally, a hauling operation will be taking place requiring a single left lane closure on I-75 SB at MM 2 and a single left lane closure on I-24 EB at MM 185. These lane closures will occur the following nights: 05/09/19 between 9 PM and 6 AM and 05/12/19 to 05/16/19 between 9 PM and 6 AM. Haul trucks will be entering and exiting the interstate at these locations.

[C.W. Matthews Contracting Company, Inc./Pruett/DB1801]

HAMILTON COUNTY US-27 (I-124) Widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge: Work on this project continues with activities occurring on the west side of southbound US-27. Motorists should be alert for construction vehicles entering and exiting the area along the access ramps for east and westbound M. L. King Boulevard. The speed limit for the access ramp is 35 MPH. The 12th Street tie-in ramp to US-27 South has been temporarily closed. This closure will be in place until further notice. Additionally, the southbound ramp from W. Main St. to southbound US-27 has been temporarily closed and will remain so until further notice. Detours are posted. Motorists should pay close attention to the detour signage posted. The speed limit on US-27 in the construction zone remains 45 MPH. Weather permitting; the contractor may implement temporary lane/shoulder closures on weeknights between the hours of 7 PM and 6 AM. At least one lane will remain open in each direction on US-27. The contractor will implement a temporary right lane closure for northbound US-27 on Thursday night (05/09/19) between the hours of 7 PM and 6 AM, from I-24 to W. 4th St. for reworking the temporary barrier rail. The westbound M.L. King Blvd. on ramp to northbound US-27 will be closed. The northbound off ramp to W. 4th St will be temporarily closed. Detours for these closures will be posted. RESTRICTIONS: I-124 (US-27)Northbound Exit 1C 4th St Off Ramp: No oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1A-B Martin Luther King Blvd. Off Ramp: No oversized/over dimensional loads; I-124 (US-27) Southbound On Ramps from Martin Luther King Blvd.: No oversized/over dimensional loads  Estimated project completion date is January 2020.

[Dement Construction Company, LLC/Micka/CNP230]

HAMILTON COUNTY TDOT Maintenance on I-75 northbound at MM 1.25: Shoulder closure trucks entering and exiting highway from right shoulder for maintenance activity on 05/09/19 from 8 AM to 4 PM.

HAMILTON COUNTY TDOT Maintenance on SR-29 (US-27) both directions at LM 11.4:   Region 2 Bridge Repair will be performing bridge maintenance on the SR-29/US-27 bridge over Falling Water Creek on Tuesday, 05/14/19, from 9 AM to 3 PM.

HAMILTON COUNTY Utility Work on SR-320 (E. BRAINERD RD.) in both directions from LM .01 to LM 4.09: Rolling lane & shoulder closures for utility work from Grays Drive to the intersection with Lee Hwy. Barrels, signage and flaggers will be present. Motorists should use caution and be aware of moving personnel and equipment as crew’s transition along SR-320 to Lee Hwy. Work will be from 05/13/19 through 05/17/19 between 9 AM to 3 PM.

HAMILTON COUNTY SR-111 Repair of bridge over SR-29 (US-27): During this report period, the contractor will have one lane closed in each direction of SR-111 while performing bridge repairs. The contractor will also be closing one lane in each direction on SR-29 as it passes under SR-111. One lane in each direction shall remain open at all times.  Estimated project completion date is October 2019.

[Mid-State Construction Company, Inc./Pruett/CNT096]

HAMILTON COUNTY SR-148 (Scenic Highway) slide repair between LM 2.3 (Sanders Road) and LM 2.5 (Linear Lane): During this report period the contractor will have one lane closed while they perform stabilization operations to the slide area. One lane of traffic shall remain open at all times. Estimated project completion date is June 2019.

[Wright Brothers Construction Company, Inc./Pruett/CNT152]

HAMILTON COUNTY SR-58 Miscellaneous safety improvements at the intersection of SR-312 (Birchwood Pike) (LM 15.70): The contractor will be completing various safety improvements at the intersection of SR-58 & Birchwood Pike Monday thru Saturday between 5 AM and 6 PM. No southbound traffic restrictions will be allowed between 5 AM and 9 AM. No northbound traffic restrictions will be allowed between 3 PM and 6 PM. Flaggers will assist with traffic control as needed. Estimated project completion date is May 2019.

[Talley Construction Company, Inc./Pruett/CNS273]

MCMINN COUNTY SR-30, Grading, drainage and paving on SR-30 from Jackson Street to east of Knight Road in Athens: All traffic has been shifted into its phase two configuration. This will involve traffic using the newly built east bound portion of SR-30. Traffic will be restricted to one lane in each direction with turning lanes provided at critical intersections and business accesses. Estimated project completion date is April 2020.

[Talley Construction Company, Inc./Micka/CNR078]

MCMINN COUNTY I-75 Resurfacing from north of County Road 267 (MM 55) to the Monroe County line (MM 60): During this reporting period, the contractor will have one lane closed in either the Southbound or Northbound direction from MM 55 to MM 60. The contractor will be working Sunday night thru Thursday night from 7 PM to 6 AM. THP will be on site to assist with traffic control. Estimated project completion date is August 2019.

[Rogers Group, Inc./Curtis/CNS330]

MCMINN COUNTY SR-305 Resurfacing from west of US-11 (SR-2) (LM 2.86) to west of I-75 (LM 5.00): The contractor will have a lane closed with flaggers directing traffic as they work. Traveling public is advised to be aware of the flaggers on the project.  Estimated project completion date is May 2019.

[Rogers Group Inc./Curtis/CNS187]

MEIGS COUNTY SR-58 Repair of bridge over Hiwassee River (LM 5.22): During this report period the contractor will have the roadway reduced to one lane controlled by temporary traffic signals. Additional flaggers will be on site as needed. Estimated project completion date is September 2019.

[Mid-State Construction Company, Inc./Pruett/CNT103]

POLK COUNTY TDOT Maintenance on SR-30 in both directions at LM 13.5: The road is currently reduced to one lane and controlled with temporary signals due to roadway settlement. TDOT geotechnical consultants are in the process of finalizing the permanent repair proposal.

[Maintenance/MAINT]

POLK COUNTY SR-40 (US-64) Repair of bridges over North Potato Creek (LM 26.93): During this reporting period, the contractor will be working to remove the existing bridge decks on both the eastbound and westbound bridges. SR-40 (US-64) is reduced to one lane in each direction for the duration of this work. RESTRICTIONS: No loads wider than 12 ft. are allowed at LM 26.93 eastbound and westbound. Estimated project completion date is April 2020.

[Jones Bros. Contractors, LLC/Curtis/CNT062]

POLK COUNTY SR-40 (US-64, US-74) Resurfacing from west of SR-30 (LM 9.8) to near Little Caney Creek Bridge (LM 13): During this reporting period, the contractor will have lane closures Monday to Friday from 8 AM to 5:30 PM for resurfacing activities. Flaggers will be present in the work zone to provide traffic control. Estimated project completion date is June 2019.

[Talley Construction Company, Inc./Curtis/CNT090]

POLK COUNTY US-64 (SR-40) Construction of a concrete bulb-tee beam bridge over Branch and TOHA Old Line railroad (LM 24.85), including grading, drainage and paving: The contractor will have intermittent lane closures Monday to Friday between 8 AM and 5:30 PM to install rumble strip and mechanical grooving on the new bridge. Estimated project completion date is May 2019.

[Talley Construction Company, Inc./Curtis/CNQ900]

RHEA COUNTY TDOT Maintenance on SR-29/US-27 (1ST ST.) in both directions from LM 22.0 to LM 22.0: Region 2 Bridge Repair will be patching the concrete deck on the SR-29 bridge over SR-68 & SOU RR on Thursday, 05/09/19, from 9 AM to 3 PM.

RHEA COUNTY TDOT Maintenance on SR-68 (WASSOM MEMORIAL HIGHWAY) in both directions at LM 5.5: The roadway is reduced to one lane and signalized 24/7 due to a roadway settlement.

[TDOT Maintenance/Maintenance/MAINT]

RHEA COUNTY SR-30 Miscellaneous safety improvements from near SR-443 (LM 4.1) to Maple Creek Drive (LM 7.75): There will be shoulder closures and possible temporary lane closures to support the installation of signs, guardrail, etc. between Monday and Friday, 6 AM to 8 PM. Estimated project completion date is July 2019.

[Superior Traffic Control, LLC/Inc./Micka/CNT075]

REGION WIDE

REGION 2 TDOT Maintenance drainage work: There will be possible short-term lane and shoulder closures at various locations in Region 2 in order to clean rock and debris from ditches on an as-needed basis. One lane will be maintained at all times.

[TDOT Operations/Maintenance/R2MAINT]

REGION 2 TDOT Maintenance pothole repair and pavement patching: There will be possible short-term emergency lane closures at various locations in Region 2 in order to repair potholes and patch pavement on an as-needed basis. Depending on location and severity these repairs may be done during the day or at night. In addition to performing the work, regional Operations crews will also provide traffic control.

[TDOT Operations/Maintenance/R2MAINT]

REGION 2 On-call guardrail repair and new guardrail installation on various interstate and state routes: The contractor may have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly from 7 PM to 6 AM Sundays through Thursdays and daily on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed.  Estimated project completion date is June 2019.

[Cumberland Guardrail, Inc./Parnham/CNS928]

REGION 2 Preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures in order to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. Work hours are 9 AM to 3:30 PM. At least one travel lane will remain open to traffic at all times. Flaggers will assist with traffic control as needed. Estimated project completion date is October 2019.

[NABCO Electric Company, Inc./Pruett/CNQ287]

REGION 2 On-call cable barrier repairs on various interstate and state routes: The contractor may have short term shoulder closures in order to perform cable rail repair. Both travel lanes will remain open to traffic at all times on the interstate during any work that is performed. Estimated project completion date is December 2019.

[R.D. Construction, LLC/Parnham/CNS282]

REGION 2 Sweeping and drain cleaning on various interstate and state routes: There will be mobile lane closures supporting a sweeping operation along regional interstates and highways through this reporting period. The sweeping activity will happen Sunday through Thursday (8 PM to 6 AM). Drain cleaning along I-75 NB (MM 2.7 to 18.0) & I-75 SB (MM 18.0-3.7) will continue Sunday through Thursday (8 PM to 6 AM). The drain cleaning activity will involve inside lane closures and some outside shoulder closures.  Estimated project completion date is February 2020.

[Blevins Enterprises, Inc./Micka/CNS320]

REGION 2 On-call pavement marking and the retracing of pavement markings with spray thermoplastic on various Interstate and State Routes: The contractor will be retracing existing pavement markings in Bradley and Hamilton Counties. This will include mobile lane closures on SR-74 and SR-311 in Bradley County, and on the following routes in Hamilton County: SR-2, SR-8, SR-17, SR-27, SR-38, SR-58, SR-60, SR-317, SR-319, SR-320, and SR-321. Motorists should be alert to all construction equipment and signage when traveling through the work zone. Estimated project completion date is June 2020.

[Central Seal Company/Cookeville/CNT047]

RESTRICTIONS

BLEDSOE COUNTY - CNS266: 10 foot lane

MARION COUNTY - CNS905: 10 foot lane

WARREN COUNTY - CNQ270: 10.5-foot max width

WARREN COUNTY - CNS254: 11-ft max width

HAMILTON COUNTY - CNP230: I-124 (US-27)Northbound Exit 1C 4th St Off Ramp: No oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1A-B Martin Luther King Blvd. Off Ramp: No oversized/over dimensional loads; I-124 (US-27) Southbound On Ramps from Martin Luther King Blvd.: No oversized/over dimensional loads

POLK COUNTY - CNT062: No loads wider than 12 ft. are allowed at LM 26.93 eastbound and westbound

                                                                                                                                                                                                                    

Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity.

Information in this report is provided to the Department of Transportation by the contractors. Most work is weather dependent and subject to change due to inclement weather. All times are local.

From your desktop or mobile device, get the latest construction activity and live streaming SmartWay traffic cameras at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any land-line or cellular phone for travel information, or follow us on Twitter at www.twitter.com/TN511 for statewide travel or Chattanooga area alerts @Chattanooga511 or any of TDOT's other Twitter pages. As always, drivers are reminded to use all motorist information tools wisely and Know Before You Go! by checking travel conditions before leaving for your destination. Drivers should never tweet, text, or talk on a cell phone while behind the wheel.

In 2016, the Tennessee Department of Transportation lost three workers in the line of duty. All three were struck by passing motorists. Those tragedies bring the total number of TDOT lives lost to 112. We don't want to lose another member of our TDOT family. We're asking you to WORK WITH US. To learn more, go to the website at https://www.tn.gov/tdot/work-with-us/.

###