Roadway Activity Report for TDOT Region 2 (Apr. 30 - May 6, 2020)

Thursday, April 30, 2020 | 02:00pm

DISTRICT 27

CUMBERLAND COUNTY I-40 Construction of a truck climbing lane EB near MM 339, including grading, drainage, and paving: Construction signs, guardrail (westbound), and portable barrier rail (eastbound) have been installed on I-40. The contractor continues grade work and will be placing base stone behind portable barrier rail. Motorists should use caution and be aware of construction personnel in the work zone and equipment that will be entering/exiting the roadway.  Estimated project completion date is September 2020.

[Charles Blalock and Sons, Inc./Bradley/CNS298]

CUMBERLAND COUNTY I-40 Resurfacing from the SR-101 ramp (LM 18) to east of SR-1 (US-70) (LM 24.6): The I-40 eastbound and westbound bridges at MM 326.5 in Cumberland County will be reduced to one lane during night time hours during this period. The contractor will be performing bridge repair work on each bridge. THP has been requested to assist with traffic control. Estimated project completion date is October 2020.

[Rogers Group, Inc./Bradley/CNT364]

CUMBERLAND COUNTY TDOT Maintenance on I-40 westbound from MM 335.6 to MM 335.7: On 05/06/20 between 7 AM and 12 PM, crews will be spot paving on I-40 Westbound near MM 335.6.

CUMBERLAND COUNTY Utility Work on SR-1 (WEST AVE.) in both directions from LM 14.17 to LM 14.63: Mobile lane closures will occur in both directions between Stanley Street and just beyond Park Street as crews transition the work zone. Signage, cones, and flaggers will be present between 8 AM to 3 PM with an estimated completion of 05/06/20.

CUMBERLAND COUNTY SR-1 (US-70) Emergency slope stabilization near LM 26.6: Construction signs, portable barrier rail, and temporary traffic signals have been installed. SR-1 (US-70) will be reduced to one lane between Godsey Road and Renegade Mountain Parkway while slope stabilization is in process. Motorists should exercise caution and pay attention to temporary traffic signals as they travel through the work zone.

[Twin K Construction/Bradley/CNT234]

CUMBERLAND COUNTY SR-101 (Peavine Road) Grading, drainage, and paving from Firetower Road to Westchester/Catoosa Boulevard: Motorists should use caution while driving along Peavine Road and be alert for shifts in traffic patterns. The posted speed limit has been reduced from 45 MPH to 35 MPH within the work zone. Base stone and paving have resumed and temporary lane closures and/or traffic stoppages may be needed as construction activities continue. Motorists should reduce speed on Peavine Road and be alert for construction personnel/equipment entering and exiting the roadway.  Estimated project completion date is November 2020.

[Rogers Group, Inc./Bradley/CNQ921]

DEKALB AND WARREN COUNTY SR-56 Construction of bridges and paving from south of Warren-Dekalb County (LM 24.5) line to East Bryant St (LM 2.9): The contractor will continue installing concrete box culverts and drainage structures. Grade work and utility work on the new roadway alignment are ongoing. No change in traffic patterns, traffic is still using the existing SR-56, however, motorists are advised to use caution and watch for construction equipment adjacent to roadway. Flaggers may be present to move equipment across roadway, unload equipment, or complete utility work.  Estimated project completion date is May 2022.

[Jones Bros. Contractors, LLC/McMinnville/CNT011]

FENTRESS COUNTY SR-52 Resurfacing (microsurfacing) from SR-296 (LM 17.6) to the Morgan County line (LM 27.9), including bridge deck and expansion joint repair; SR-296 resurfacing (microsurfacing) from SR-28 (US-127) (LM 0) to SR-52 (LM 3); and SR-28 (US-127) resurfacing (microsurfacing) from south of Airport Road (LM 13.3) to near the Old US-127S ramp (LM 16.9): The contractor is scheduled to begin paving operations on 05/11/20 on SR-52 from LM 17.6 to 27.9 and on SR-296 from LM 0.0 to LM 3.0. During this work, the contractor will use a mobile operation and will have the roadway reduced to one lane. Flaggers will be used along with a pace vehicle to control the flow of traffic through the work zone. Estimated project completion date is September 2020.

[American Pavements, Inc./Moore/CNU031]

FENTRESS AND OVERTON COUNTY SR-85 Emergency slide repairs at various locations: The contractor continues work on the Overton County side of SR-85 and the road remains closed from LM 17.5 to LM 22.2. This closure will remain in effect until the project completion scheduled for 09/30/20. The Fentress County portion of SR-85 remains open to through traffic. A detour route remains in place for Overton SR-85 and motorists are encouraged to continue using the detour route until the road is opened. Estimated project completion date is September 2020.

[Wright Brothers Construction Company, Inc./Moore/CNT154]

JACKSON COUNTY SR-85 Resurfacing (microsurfacing) from the Smith County line (LM 0) to SR-56 (LM 15.3) and SR-262 resurfacing (microsurfacing) from the Macon County line (LM 0) to the Cumberland River Bridge (LM 7.5): The contractor will begin guardrail work on 05/04/20. During this work, one lane will be closed at various locations. Flaggers and advanced warning signs will be utilized for this work. The contractor is scheduled to begin paving work on 05/12/20 and will use flaggers to control the flow of traffic through the work zone. Motorists are encouraged to use caution in the work zone and obey posted speed limits. Estimated project completion date is September 2020.

[Hudson Construction Company/Moore/CNU067]

OVERTON COUNTY SR-294 Bridge repair over Big Eagle Creek (LM 1.39): The lane closure at LM 1.39 remains in place and will last until project completion scheduled for 06/15/20. The contractor has begun work on Phase 2 of the project and a temporary signal system remains in place to allow traffic through the work zone. Motorists are encouraged to use caution and move slowly through the work zone when the signal light allows. RESTRICTIONS: Loads wider than 9.5' should seek alternate route.  Estimated project completion date is June 2020.

[W and O Construction Company, Inc./Moore/CNT243]

OVERTON COUNTY S.I.A. Grading, drainage and paving on Oak Hill Road from Rickman Road to near SR-111: The contractor currently has Oak Hill Road closed to traffic. This road closure is scheduled to remain in place until project completion scheduled for 06/30/20. The closure of Oak Hill Road will begin just past the Tanimura Plant entrance and end at first entrance of Fitzgerald's Plant. During this closure, motorists wishing to access Tanimura Plant should do so from SR-111 side; motorists wishing to access Fitzgerald's should do so from Old SR-42/Rickman Road. A detour route will be in place along SR-293 to allow motorists to bypass Oak Hill Road. Estimated project completion date is June 2020.

[Rogers Group, Inc./Moore/CNT017]

PUTNAM COUNTY TDOT Maintenance on I-40 westbound at MM 298.7: On 05/06/20 between 12 PM and 4 PM, crews will be spot paving on I-40 around MM 298.7.

PUTNAM COUNTY Utility Work on I-40 in both directions from MM 20.70 to MM 20.70: A THP rolling road block will occur on I-40 from E. Spring Street to S. Willow Avenue. Motorists should be prepared to stop and be alert of all traffic signage, personnel, and equipment. This rolling road block will take place between 9:30 AM and 11:30 AM on 05/06/20.

PUTNAM COUNTY Utility Work on SR-111 (STATE HWY. 111) in both directions from LM 2.55 to LM 2.55: A THP rolling road block will occur on SR 111 from Salem Road to SR 136. Motorists should be prepared to stop and be alert of all traffic signage, personnel, and equipment. This rolling road block will take place between 9:30 AM and 10:00 AM on 05/05/20.

PUTNAM COUNTY Utility Work on SR-135 (S. WILLOW AVE.) in both directions from LM 9.7 to LM 8.4: Lane closures will occur between I-40 and State Street with signage, barrels and cones. Motorists should use caution and be aware of personnel and equipment when traveling through the work zones. Traffic may be reduced to a single lane in some locations from 9 AM to 3 PM, Monday through Friday with estimated completion date of 06/30/20.

PUTNAM COUNTY SR-136 Resurfacing from US-70N (SR-24) (LM 4.15) to north of Whiteaker Springs Road (LM 7): The contractor will begin milling operations during the day, resulting in daily lane closures from 12th Street (LM 5.35) to north of Whiteaker Springs Road (LM 7.00). Motorists are advised to use caution while traveling through the work zone and be alert of all traffic signage, personnel, and equipment. Estimated project completion date is June 2020.

[Rogers Group, Inc./Cookeville/CNT920]

WHITE COUNTY Grading, drainage and paving at Airport Rd. leading up to Upper Cumberland Regional Airport: The contractor will be working on grading and drainage work along Technology Drive and Airport Road during this period. Temporary traffic stoppages may be needed as construction progresses. Motorists are advised to use caution while traveling through the work zone and be alert of all traffic signage, personnel, and equipment. Estimated project completion date is June 2020.

[Rogers Group, Inc./Cookeville/CNT259]

 

DISTRICT 28

BLEDSOE COUNTY SR-28 Slope stabilization in Bledsoe County near LM 28.8: The contractor is working on SR-28 north from LM 28.7 to 28.9. Large trucks heading South on SR-28, down the mountain are encouraged to use extreme caution. Estimated project completion date is May 2020.

[Twin K Construction/Voiles/CNT924]

BLEDSOE AND SEQUATCHIE COUNTY Resurfacing on SR-30 in Bledsoe County and on SR-8 (US-127) and SR-28 (US-127) in Sequatchie County: During this reporting period, the contractor will be performing resurfacing operations. The roadway will be reduced to one lane during the day while this work is ongoing. Motorists are encouraged to use caution in the work zone and watch for equipment and personnel in the roadway. Estimated project completion date is June 2020.

[Rogers Group, Inc./Voiles/CNT918]

COFFEE COUNTY Utility Work on I-24 westbound near MM 114: A lane closure of the Westbound on ramp of I-24 off of Hillsboro Blvd. will occur for aerial crossings. Motorists should use caution and be aware of personnel and equipment when traveling through the work zones. Work will take place on 05/05/20 from 9 AM to 10:30 AM.

COFFEE COUNTY SR-55 Resurfacing (microsurfacing) from north of HP Womack Road (LM 7.4) to south of Kennedy Drive (LM 11.4): Construction signs have been installed. During this reporting period, the contractor will be working to remove snowplowable markers and removal of striping. Additionally, fog sealing shoulders will take place throughout the project. This work will occur weather permitting. Motorists are advised to use caution while traveling through the work zone and be alert of all traffic signage, personnel, and equipment.  Estimated project completion date is September 2020.

[American Pavements, Inc./Hussein/CNU023]

FRANKLIN COUNTY Utility Work on SR-127 (AEDC RD.) in both directions from LM 4.1 to LM 4.5: Intermittent lane closures will occur between the Scenic View Golf Course and Paynes Church Rd. Signage and flaggers will be present. Motorists should be aware of personnel and equipment between 9 AM and 3 PM with an estimated completion date of 05/22/20.

FRANKLIN COUNTY Utility Work on SR-16 (US-41A) in both directions from LM 9.82 to LM 6.33: Intermittent lane closures will occur between Blair Pond Road and Beth Page Road. Signage and flaggers will be present, motorists should be aware of personnel and equipment between 9 AM and 3 PM with an estimated completion of 05/25/20.

GRUNDY COUNTY I-24 Resurfacing from east of Bells Mill Road (MM 129.1) to west of the Rest Area (MM 129.4): Tentatively the contractor is scheduled to begin installation of construction signs throughout the project. Motorists are advised to use caution while traveling through the work zone and be alert of all traffic signage, personnel, and equipment.  Estimated project completion date is August 2020.

[Rogers Group, Inc./Hussein/CNT376]

GRUNDY COUNTY SR-108 Repair of the bridge over Branch (LM 28.2): Work continues on phase one of this project. The project will continue to have a temporary traffic signals installed reducing the roadway to one, 10 ft. travel lane. The lane closure will remain until project completion scheduled for 05/31/21. Motorists are advised to use caution while traveling through the work zone and be alert of all traffic signage, personnel, and equipment. RESTRICTIONS: Loads wider than 10' should seek alternate route.  Estimated project completion date is May 2021.

[Jamison Construction/Hussein/CNT397]

GRUNDY COUNTY SR-56 Slide repair from LM 25.9 to LM 26.1: Traffic will be reduced to one lane on SR-56 with traffic signals in place while roadway repairs are being completed.  Estimated project completion date is May 2020.

[TDOT/Miner/MAINT]

MARION COUNTY TDOT Maintenance on SR-156 (SOUTH PITTSBURG MTN. RD.) in both directions from LM 13.5 to LM 13.6: The roadway has been reduced to one lane with traffic signals in place for washout repairs.

MARION COUNTY Utility Work on SR-150 (US-41) in both directions from LM 2.98 to LM 11.51: Lane closures will occur along SR-150 with signage, flaggers, barrels and cones. Motorists should use caution and be aware of personnel and equipment when traveling through the work zones. Traffic may be reduced to a single lane in some locations for aerial crossings between 8 AM and 2 PM, with an estimated completion date of 05/19/20.

MARION COUNTY SR-150 in both directions at LM 4.7: Traffic is reduced to one lane with traffic signals in place for a slide repair.

[TDOT/Miner/MAINT]

MARION COUNTY SR-2 (US-64, US-72, US-41) Emergency slope stabilization between LM 25.20 and LM 26.40: The contractor will continue to maintain one lane of travel open to traffic with the restriction of all wide loads. At this time, traffic signals are installed and will remain in place until the project is complete. Motorists are encouraged to use caution and be alert to construction personnel and equipment. RESTRICTIONS: The restriction of all wide loads will remain in place until project is complete.

[Dement Construction Company, LLC/Hussein/CNT229]

MARION COUNTY TDOT Contractor on SR-2 (US-41) in both directions at LM 30.9: Traffic is reduced to one lane with traffic signals in place for a slide repair.

[TDOT/Miner/MAINT]

SEQUATCHIE COUNTY Utility Work on SR-8 (HWY. 8) in both directions from LM 29.82 to LM 29.82: Lane closures will occur along SR-8 with signage, and flaggers. Motorists should be prepared to stop to allow for an aerial crossing and be aware of personnel and equipment when traveling through the work zones. The work will take place between 9 AM and 10 AM on 05/06/20.

VANBUREN COUNTY SR-30 Slope stabilization near LM 16.1: The contractor is working on SR-30 North from LM 15.9 to 16.3. The roadway will be reduced to one lane controlled by a traffic signal. Large trucks heading West on SR-30, down the mountain are encouraged to use extreme caution. Estimated project completion date is June 2020.

[Twin K Construction/Voiles/CNT924]

WARREN COUNTY SR-288 Construction of a concrete bulb-tee beam bridge over Collins River (LM 4.97), including grading, drainage and paving: Both lanes of the bridge are now open. Motorists should use caution in the work zone and watch for workers. If necessary, flaggers may be present to complete any remaining work. Estimated project completion date is May 2020.

[Palmertree Construction Company, LLC/McMinnville/CNQ270]

 

DISTRICT 29

BRADLEY COUNTY TDOT Contractor on I-75 in both directions from MM 14.2 to MM 18: From 05/04/20 to 05/08/20, the contractor will have shoulder closures on White Oak mountain from 9 AM - 3:30 PM EST. Closures are for survey field work (traverse along the shoulder) to be completed. From 05/11/20 to 05/15/20, there will be a nighttime mobile operation for the inside lanes of I-75 to gather information on the storm structures. Traffic control will be in place. This work is weather permitting. [CIA ENGINEERS/PRUETT]

BRADLEY COUNTY Utility Work on SR-2 (N. LEE HWY.) southbound from LM 14.91 to LM 15.05: A shoulder and single lane closure will occur between Anatole Ln NW and 56th Street NW. Signage and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 3 PM from 03/23/20 through 05/06/20.

HAMILTON COUNTY I-24 Replacement of the Belvoir Ave. Bridge over I-24 and I-24 bridges over Germantown Road near MM 183: Lane shifts are in place on I-24 at the Belvoir Avenue Bridge. The contractor will continue night time removal of median barrier on I-24 under Belvoir Avenue Bridge. Single interior lane closures will occur EB and WB between MM 182 and 184 between 9 PM and 6 AM on Thursday 04/30/20 and resuming between Sunday 05/03/20 and Wednesday 05/06/2020. There will be night time lane closures in the northbound and southbound directions of Germantown Rd. under the I-24 Bridge and at the intersections with North and South Terrace. Single lane closures will occur between 9 PM and 6 AM on Thursday 04/30/20 and resuming between Sunday 05/03/20 and Wednesday 05/06/2020. Additionally, motorists should be aware of the Belvoir Ave. Bridge closure and detour that was put into place on April 20. There is a 45 MPH speed limit reduction throughout the project corridor on I-24. Estimated project completion date is August 2021.

[Bell and Associates Construction, LP/Blevins/CMGC03]

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction: Watch for trucks entering and exiting project. Phase 1 traffic shifts have been implemented. Traffic should expect multiple lane shifts traveling through the interchange. Lane closures will occur Sunday nights through Thursday nights between 9 PM and 6 AM at the following locations: I-75 NB MM 1, I-75 SB MM 3 and I-24 EB MM 184.0 Traffic pacing may occur to set bridge beams throughout interchange Sunday nights through Thursday nights between 9 PM and 6 AM. Additionally, there may intermittent shoulder closures at various locations for access to the median and roadside areas. The speed limit has been reduced to 45 MPH throughout the interchange.

[C.W. Matthews Contracting Company, Inc./Blevins/DB1801]

HAMILTON COUNTY TDOT Contractor on I-75 both directions from MM 4 to MM 6: Starting on 04/20/20 and lasting for approximately three to four weeks, geotechnical crews will be conducting drilling operations during daytime hours to evaluate the soil conditions in this area for a future improvement project. A majority of this work will take place off of the roadway but may require some short-term shoulder closures. Workers will be present in this area.

[S and ME/Maintenance/MAINT]

HAMILTON COUNTY US-27 (I-124) Widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge: On 05/02/20, from 7AM to 7PM, temporary lane closures will be in place for southbound US-27 from the Olgiati Bridge to I-24 for shifting southbound traffic onto the new alignment of US-27 southbound. During this closure, there will be intermittent southbound ramp closures. During these ramp closures, downtown traffic will be detoured to Manufacturers Rd. /Cherokee Blvd. to Market St. southbound or alternately to eastbound I-24 to the Broad St. exit. During the southbound US-27 Ramp to westbound I-24 Ramp closure, traffic will be detoured to eastbound I-24/4th Ave. exit to westbound I-24. RESTRICTIONS: I-124 (US-27) Northbound Exit 1C 4th St Off Ramp: No oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1C 4th St Of Ramp: On oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1B East Martin Luther King Blvd. Off Ramp: No oversized/over dimensional loads; I-124 (US-27) Southbound On Ramps from Martin Luther King Blvd.: No oversized/over dimensional loads.

[Dement Construction Company, LLC/Micka/CNP230]

HAMILTON COUNTY TDOT Bridge Maintenance on I-24 eastbound at MM 181: On Wednesday of this reporting period from 9 PM- 6 AM, the outside lane will be closed at MM 181 and Exit 181A due to maintenance work on the bridge approach.

HAMILTON COUNTY TDOT Bridge Maintenance on I-24 westbound from MM 184 to MM 184: A region 2 bridge maintenance crew will be repairing a pothole on I-24, MM 184, just before the ridge cut. This will be a nighttime operation from 9:00 PM-6:00 AM. The #1 lane will be closed during this project.

HAMILTON COUNTY TDOT Contractor on SR-8 (US-127/SIGNAL MOUNTAIN BLVD.) in both directions from LM 14 to LM 16.5: Beginning on 04/01/20, geotechnical contract crews will begin conducting drilling operations to evaluate the roadway for a future improvement project. These operations are estimated to continue on weekdays during daytime hours for approximately five weeks. The contractor will begin work at 9 AM each day and work as long as possible. There are ten sites between SR-27/Suck Creek Rd. to past Shoal Creek Rd. that the contactor will be investigating during this time period. During drilling operations, the roadway will be temporarily reduced to one lane. Drivers are encouraged to be patient and alert as they travel through the work zone. Estimated project completion date is May 2020.

[S and ME/Maintenance/MAINT]

HAMILTON COUNTY Utility Work on SR-2 (BROAD ST.) southbound from LM 6.31 to LM 6.31: A shoulder and single lane closure will occur between W. 32nd Street and Watson Street at 3201 Broad Street. Signage and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 3 PM from 04/13/20 through 05/06/20.

HAMILTON COUNTY Utility Work on SR-319 (HIXSON PK.) eastbound from LM 7.16 to LM 7.16: A shoulder and single lane closure will occur between Templeton Lane and Cassandra Smith Road at 5993 Hixson Pike. Signage and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 3 PM from 04/20/20 through 05/06/20.

HAMILTON COUNTY Utility Work on SR-320 (E. BRAINERD RD.) westbound from LM 2.74 to LM 3.47: A shoulder closure will occur along E. Brainerd Road to pave recent pavement cuts. Signage and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 3 PM on 04/30/20.

HAMILTON COUNTY SR-2 (US-64, US-11) Improvement of the intersection at Edgmon Road in Collegedale (LM 22.7), including grading, drainage and paving: During this report period, the contractor will be working primarily on the shoulders and no lane restrictions are expected. Extra care should be taken while trucks are entering and exiting the roadway. Additional flaggers will be onsite as needed. Estimated project completion date is May 2021.

[Talley Construction Company, Inc./Osbonlighter/CNU012]

HAMILTON COUNTY SR-317 (Apison Pike) Improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: The contractor has installed a lane shift on SR-317 (Apison Pike) near the intersection of SR‑321 (Ooltewah-Ringgold Rd.) at the current four-lane section. Two lanes will remain open at all times. Utility work is currently taking place and flaggers will assist with traffic control as necessary to allow for equipment and materials delivery. Estimated project completion date is June 2025.

[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]

HAMILTON COUNTY SR-8 (US-127/SIGNAL MOUNTAIN BLVD.) in both directions from Space House to bottom of mountain: Due to the road being washed out, traffic has been reduced to one lane in each direction at this location.

[GeoStabilization International, LLC /Maintenance/MAINT]

MCMINN COUNTY SR-30, Grading, drainage and paving on SR-30 from Jackson Street to east of Knight Road in Athens: All SR-30 traffic is in the project's final alignment. There may be temporary outside lane and shoulder closures to support the completion of punch list items through this reporting period.

[Talley Construction Company, Inc./Micka/CNR078]

MEIGS COUNTY SR-58 Repair of bridge over Hiwassee River (LM 5.22): During this report period, the contractor will have the roadway reduced to one lane controlled by temporary traffic signals. Additional flaggers will be on site as needed.

[Mid-State Construction Company, Inc./Osbonlighter/CNT103]

POLK COUNTY SR-30 Resurfacing from Greasy Creek Road (LM 13.1) to north of US-64 (US-74, SR-40) (LM 17.17): During this reporting period, the contractor will be working on resurfacing operations on SR-30. Daily lane closures will be in effect on SR-30 from 8 AM to 5 PM. Motorists are advised to expect long delays in the work zone during these times and seek an alternate route when possible.  Estimated project completion date is October 2020.

[Talley Construction Company, Inc./Wagner/CNU022]

POLK COUNTY SR-40 (US-64) Repair of bridges over North Potato Creek (LM 26.93): During this reporting period, the contractor will be working on the installation of a new concrete overlay on the westbound bridge and new approach slabs on the eastbound bridge. Traffic is reduced to one lane in each direction on US-64 for the duration of this work. Motorists are advised to reduce speed and use caution in the work zone due to reduced lane widths. RESTRICTIONS: 12 ft. maximum width LM 26.93 Westbound 14 ft. maximum width LM 26.93 Eastbound.

[Jones Bros. Contractors, LLC/Wagner/CNT062]

POLK COUNTY Boanerges Church Road construction of a bridge over Old Fort Creek: During this reporting period, the contractor will be working to install portions of the new bridge. This work will occur weather permitting. Boanerges Church Road is closed to all traffic for the duration of construction. Detour signs are posted diverting traffic around the closure onto SR-313 and US-411.  Estimated project completion date is October 2020.

[Summers-Taylor, Inc./Wagner/CNT279]

RHEA COUNTY SR-30 Grading, drainage and paving from west of New Union Road/White Oak Road (LM 12.6) to Sky Drive (LM 12.9): During this report period, the contractor will be performing grading & drainage operations along SR-30, New Union Rd & White Oak Dr. During this current phase, a new traffic pattern will be in place at SR-30; SR-30 will be shifting from the current alignment to the new alignment. The intersections of White Oak Drive and New Union Road will be shifted to the new portion of SR-30. Flaggers will be on-site to assist with heavy equipment entering and exiting existing roadways.

[Twin K Construction/Osbonlighter/CNT073]

RHEA COUNTY Grading, drainage, construction of bridges, paving and signals on a S.I.A. route serving Nokian Tyres There is a lane shift set up for all NB & SB SR-29 traffic in front of the proposed Nokian Tyres SIA entrance. This is expected to persist for the duration of the project. Additionally, there could be lane closures to support construction at the Manufacturers Rd/SR-29 intersection.  Estimated project completion date is October 2022.

[Dement Construction Company, LLC/Micka/CNU014]

 

REGION WIDE

REGION 2 TDOT Maintenance drainage work: There will be possible short-term lane and shoulder closures at various locations in Region 2 in order to clean rock and debris from ditches on an as-needed basis. One lane will be maintained at all times.

[TDOT Operations/Maintenance/R2MAINT]

REGION 2 TDOT Maintenance pothole repair and pavement patching: There will be possible short-term emergency lane closures at various locations in Region 2 in order to repair potholes and patch pavement on an as-needed basis. Depending on location and severity these repairs may be done during the day or at night. In addition to performing the work, regional Operations crews will also provide traffic control.

[TDOT Operations/Maintenance/R2MAINT]

REGION 2 On-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor may have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly from 7 PM to 6 AM Sundays through Thursdays and daily on state routes. At least one travel lane will remain open to traffic at all times on the interstate, and flaggers will be present on state routes during any work that is performed. Estimated project completion date is June 2020.

[Cumberland Guardrail, Inc./McMinnville/CNT114]

REGION 2 Preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures in order to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. Work hours are 9 AM to 3:30 PM. At least one travel lane will remain open to traffic at all times. Flaggers will assist with traffic control as needed.  Estimated project completion date is January 2023.

[NABCO Electric Company, Inc./Osbonlighter/CNT354]

REGION 2 Sweeping and drain cleaning on various interstate and state routes: There will be a drain cleaning operation in Hamilton County along I-75 northbound (MM 10 -MM 17) & I-75 SB (MM 17 - MM 13) that will involve closing the inside lane for up to one mile intervals. Additionally, a sweeping operation supported by mobile lane closures will happen throughout the region on interstates & selected state routes. Both operations will happen Sunday - Thursday (9 PM -6 AM).  Estimated project completion date is April 2020.

[Blevins Enterprises, Inc./Micka/CNS320]

REGION 2 On-call cable barrier repair on various Interstate and State Routes: The contractor may have short term shoulder closures in order to perform cable rail repair. Both travel lanes will remain open to traffic at all times on the interstate during any work that is performed. Estimated project completion date is December 2020.

[LU, Inc./McMinnville/CNT292]

REGION 2 On-call pavement marking and the retracing of pavement markings with spray thermoplastic on various Interstate and State Routes: The contractor will be installing snowplowable markers in Bradley County on SR-60 (LM 8.22 - 10.96), in Jackson County on SR-53 (LM 0.00 - 3.90) and in Grundy County on SR-56 (LM 18.9 - 19.0). The contractor will also be removing and replacing various pavement markings at the intersection of SR-60, SR-306, and Freewill Road in Bradley County (SR-60 LM 19.9). Motorists should expect brief stoppages in traffic and be aware of all construction signage and equipment. Estimated project completion date is June 2020.

[Central Seal Company/Cookeville/CNT047]

REGION 2 Relensing of snowplowable pavement markers on various Interstate and State Routes: The contractor will be performing temporary lane closures to replace snowplowable pavement markers on various routes throughout Coffee and Warren Counties. Coffee County routes include I-24, SR-2, SR-16, SR-50, SR-53, SR-55, SR-64, SR-127, SR-130, SR-269, and SR-280. Warren County routes include SR-1, SR-8, SR-30, SR-55, SR-56, SR-108, SR-127, SR-136, SR-287, SR-288, and SR-380. Motorists are advised to use caution while traveling through the work zone and be alert of all traffic signage, personnel, and equipment. Estimated project completion date is November 2020.

[W.L. Markers Inc./Cookeville/CNU068]

 

RESTRICTIONS

OVERTON COUNTY - CNT243: Loads wider than 9.5' should seek alternate route.

GRUNDY COUNTY - CNT397: Loads wider than 10' should seek alternate route.

MARION COUNTY - CNT229: Restriction of all wide loads will remain in place until project is complete.

HAMILTON COUNTY - CNP230: I-124 (US-27) Northbound Exit 1C 4th St Off Ramp: No oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1C 4th St Of Ramp: On oversize/over dimensional loads; I-124 (US-27) Southbound Exit 1B East Martin Luther King Blvd. Off Ramp: No oversized/over dimensional loads; I-124 (US-27) Southbound On Ramps from Martin Luther King Blvd.: No oversized/over dimensional loads.

POLK COUNTY - CNT062: 12 ft. maximum width LM 26.93 Westbound 14 ft. maximum width LM 26.93 Eastbound.

Motorists are encouraged to use caution and obey reduced speed limits in all TDOT work zones, regardless of lane closure activity.

Information in this report is provided to the Department of Transportation by the contractors. Most work is weather dependent and subject to change due to inclement weather. All times are local.

From your desktop or mobile device, get the latest construction activity and live streaming SmartWay traffic cameras at www.TNSmartWay.com/Traffic. Travelers can also dial 511 from any land-line or cellular phone for travel information, or follow us on Twitter at www.twitter.com/TN511 for statewide travel or Chattanooga area alerts @Chattanooga511 or any of TDOT's other Twitter pages. As always, drivers are reminded to use all motorist information tools wisely and Know Before You Go! by checking travel conditions before leaving for your destination. Drivers should never tweet, text, or talk on a cell phone while behind the wheel.

In 2016, the Tennessee Department of Transportation lost three workers in the line of duty. All three were struck by passing motorists. Those tragedies bring the total number of TDOT lives lost to 112. We don't want to lose another member of our TDOT family. We're asking you to WORK WITH US. To learn more, go to the website at https://www.tn.gov/tdot/work-with-us/.

###