Region 2 Lane Closure Report for June 27-July 3, 2024

Thursday, June 27, 2024 | 08:57am

ROADWAY ACTIVITY REPORT – REGION 2
(Parts of East and Middle Tennessee)
June 27-July 3, 2024

DISTRICT 27

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): The contractor continues grading activities throughout the project limits. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. The contractor is scheduled to close North Grace Hill Drive at the existing intersection of SR-28 (US-127) beginning on 07/01/24 for construction activities. Motorists should utilize South Grace Hill Drive as the detour with appropriate signs. Flaggers and advanced warning signs will accompany any closures. Motorists should use caution while traveling through the work zone.
[Jones Bros. Contractors, LLC/Crossville/CNV009]

CUMBERLAND COUNTY SR-1 (SPARTA HWY.) Utility Work both directions from LM 1.83 to LM 4.88: Intermittent stoppages as well as shoulder and lane closures on SR-1 (Sparta Hwy) between East Main Pleasant Hill and Arthur Seagraves Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 04/18/24 through 06/26/24 from 8 am to 3 pm. [2024-182]
 

CUMBERLAND COUNTY SR-1 (US-70 E.) Utility Work both directions from LM 17.22 to LM 22.57: Intermittent stoppages as well as shoulder and lane closures on SR-1 (US-70) between the intersection of SR-101/SR392 to west of Sky Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 06/27/24 through 07/26/24 from 8 am to 3 pm. [2024-280]
 

CUMBERLAND COUNTY SR-1 (US-70) construction of a roundabout at SR-392 (LM 17 / Milo Lemert Parkway) and SR-101 (Peavine Rd / 17.4): Construction activities are ongoing. Lane closures may be necessary to complete the work. Appropriate signs will be utilized. Motorists entering the roundabout should yield to vehicles within the roundabout. Motorists should use caution while driving through the work zone.
[Mack Construction, LLC/Crossville/CNW373]
 

CUMBERLAND COUNTY SR-1 (US-70) construction of bridge over the Obed River (LM 12.7): Bridge replacement activities continue SR-1 (US-70) over the Obed River bridge. SR-1 (US-70) is to be closed at the bridge for the duration of the project until the work is completed. A detour with signs has been displayed to utilize Northside Drive (SR-462) to travel around the closure. Additionally, the left turn from Sparta Drive onto Miller Avenue (SR-392) has been closed for the duration of the project. Motorists should be aware of the road closure and utilize the detour route as necessary. RESTRICTIONS: Bridge on SR-1 (US-70) over the Obed River is being replaced. The road is closed at LM 12.72.
[Whaley Construction, LLC/Crossville/CNX110]
 

CUMBERLAND COUNTY SR-1 resurfacing from LM 16.29 to LM 28: The contractor will be micro surfacing on SR-1 from LM 16.29 - 28.00. During this work the contractor will have lane closures in place and flaggers present. Motorists can expect slight delays in travel and are encouraged to use caution and follow all construction signing and flagger commands.
[Asphalt Paving Systems, Inc./Cookeville/CNY902]
 

CUMBERLAND COUNTY SR-101 resurfacing from south of SR-282 (Dunbar Lane, LM 12.4) to SR-1 (US-70, LM 15.9): Construction activities are ongoing. Contractor is working on sidewalks and curb ramps. Shoulder and/or lane closures may be necessary to complete the work. The contractor will be working on the intersection of SR-1 (US-70) and Lantana Road near LM 15.9 during the night. Appropriate signs will be utilized to direct traffic. Motorists should use caution while driving through the work zone.
[Rogers Group, Inc./Crossville/CNY010]
 

CUMBERLAND COUNTY SR-28 (Main Street, US-127) downtown pedestrian improvement project between Lantana Road (Highway 70 East) and Neecham Street: Construction activities are ongoing along SR-28 (Main Street). The contractor is working on removing and replacing the concrete sidewalk and curb ramps North from Lantana Road to near West 2nd Street. The shoulder parking along this area has been closed. Lane closures may be required at times for construction activities. Signs and flaggers may be utilized during these lane closures and/or lane shifts. Motorists should use caution when traveling through the work zone.
[Adams Contracting, LLC/Crossville/LP24_1]
 

CUMBERLAND COUNTY SR-28 (US-127) grading, drainage, signals and paving from SR-68 to south of the bridge over Byrd's Creek (LM 9.7 to LM 10.6): Construction activities are in progress along SR-28 and SR-68. Construction equipment and vehicles will be entering and exiting the work zone frequently. Motorists should use caution when traveling through the area and be aware of the traffic pattern shifts.
[Cleary Construction, Inc./Crossville/CNW231]
 

CUMBERLAND COUNTY SR-298 resurfacing from near Jackie Drive (LM 2.7) to east of Lake Francis Road (LM 6.8): Resurfacing operations are ongoing. One lane will be closed while resurfacing activities are ongoing. Motorists should be cautious of the daily flagging operations. Flaggers and advanced warning signs will be displayed to alert motorists of the traffic conditions.
[Rogers Group, Inc./Crossville/CNY103]
 

CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: Construction activities are in progress. Activities will require temporary lane closures and/or traffic stoppages on Interstate Drive (SR-462), as well as short term closures of city streets. Flagging operations will accompany these closures with appropriate signs. The right shoulder of SR-28 Northbound near the intersection of Interstate Drive has been closed. Motorists traveling west on Interstate Drive should be mindful of the "Right Turn Only" lane at the intersection of Stout Drive. Motorists should use caution when traveling through the work zone.
[Rogers Group, Inc./Crossville/CNV010]
 

CUMBERLAND AND FENTRESS COUNTY SR-28 (US-127) widening from near N. Lowe Rd (LM 29.2) to north of SR-62 (LM 1.9): The contractor will continue work along the new alignment of SR 28. In addition, the contractor will be performing utility work adjacent to the existing alignment of SR 28. Flaggers are being intermittently used to control traffic through parts of the work zone. Motorists are encouraged to use caution and watch for construction equipment and personnel adjacent to the roadway.
[Jones Bros. Contractors, LLC/Cookeville/CNV300]
 

DEKALB COUNTY SR-141 (LANCASTER RD.) TDOT Maintenance both directions at LM 0.43: TDOT will be performing slide repairs on SR-141 at LM 0.43. The roadway is closed. Motorists are encouraged to use caution in the area and should follow all construction and detour signs. RESTRICTIONS: The road is closed at LM 0.43 near the Smith - Dekalb County line.
 

DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor continues grading and construction activities throughout the project. Temporary lane closures and periodic traffic stoppages will be necessary for construction activities and motorists should be prepared to stop while traveling through the work zone. Motorists are encouraged to obey posted speed limit and to watch for construction equipment and personnel adjacent to the roadway. The West end of Old Liberty Road will be closed to through traffic due to construction activities. Motorists and EMS will need to use the East entrance of Old Liberty Road to gain access and follow detour signs.
[Twin K Construction/Cookeville/CNV012]
 

JACKSON COUNTY SR-135 rockfall mitigation north of Daniel Hill Lane (LM 7.1): The contractor has begun clearing and rockfall mitigation work. SR-135 is closed from LM 6.31 – 7.76. Message boards and detour routes are in place. Motorists are encouraged to use caution and follow detour signage. RESTRICTIONS: Closed with detour in place.
[Tim's Tree Service, Inc./Livingston/CNX406]

 

JACKSON COUNTY SR-85 bridge repair over Indian Creek (LM 4.77): The contractor continues bridge repair work. The road is reduced to one 11’ lane from LM 4.5 – 5.0 using temporary traffic signals to control traffic through the work zone. A wide load detour is in place for vehicles that require larger clearance. Motorists are encouraged to use caution and watch for construction equipment and personnel throughout the work zone. RESTRICTIONS: The road is reduced to one 11’ lane from LM 4.5 – 5.0 using temporary traffic signals to control traffic through the work zone.
[Thomson and Thomson, Inc./Livingston/CNX111]
 

PUTNAM COUNTY SR-136 construction from north of the SR-111 interchange to south of the I-40 interchange: The contractor continues grading activities throughout the project. Temporary lane closures and/or periodic traffic stoppages will be necessary for construction activities. Pigeon Roost Creek Road and Messenger Road are closed at the intersection of SR-136 with detour signs to utilize Bunker Hill Road. In addition, the turning lane serving Prescott South Middle School has been taken out of service and northbound Jefferson Avenue will be restricted to one lane. Motorists are encouraged to use caution while traveling through the work zone and be aware of construction personnel.
[Rogers Group, Inc./Cookeville/CNV284]
 

PUTNAM COUNTY I-40 from east of SR-56 (MM 274) to east of SR-56 (MM 281): The contractor will be milling and paving from 7 PM to 6 AM weather permitting from Sunday through Thursday nights. The on and off-ramps located at MM 276 and MM 280 will also be closed intermittently. One lane in each direction will be closed during this work, and motorists are encouraged to use caution and to be prepared to stop as they approach the work zone.
[Vulcan Construction Materials, LLC/Cookeville/CNX410]
 

WHITE COUNTY SR-111 resurfacing from Van Buren County Line (LM 0) to near Shady Oak Rd (LM 4.2): The contractor will be on site removing snow plowable markers and removing thermoplastic pavement markings on SR-111 from LM 0.00 - 4.20. During this work lane closures may be used, and motorists can expect delays. Motorists are encouraged to use caution when contractor crews are present.
[Asphalt Paving Systems, Inc./Cookeville/CNY902]
 

DISTRICT 28
 

BLEDSOE COUNTY SR-28 (MAIN ST.) TDOT Maintenance northbound at LM 15.62: Right Lane is currently shut down to one lane. investigating a possible sink hole. Further information when available. 6/25/24 24 hours /7days RESTRICTIONS: No restrictions currently.
 

BLEDSOE COUNTY SR-30 (STATE HWY. 30) TDOT Bridge Inspection southbound from LM 10.35 to LM 10.36: A routine inspection of Veterans Memorial Bridge on SR-30 over the Sequatchie River in Pikeville will be conducted between 8:00 AM and 3:00 PM on Tuesday, July 2, 2024. Motorists are advised to use caution and watch for flaggers who will direct traffic through the work zone.
 

CANNON COUNTY SR-1 (US-70S) construction from near Barker Road (LM 1.2) to east of Hoover Road (LM 2.5): Contractor may be utilizing rolling roadblocks and lane closures through the work zone for signal work. Motorists should expect delays and remain vigilant of traffic control measures and use caution at the intersection of SR-64 and SR-1.
[Tinsley Asphalt, LLC /McMinnville/CNW348]\\
 

COFFEE COUNTY SR-55 (E. CARROLL ST.) Utility Work both directions from LM 5.236 to LM 3.016: Police assisted rolling roadblock on SR-55 (E. Carroll Street) between S. Anderson Street and Cobb Road. Motorists should reduce speed and be prepared to stop. Trucks, signage and barrels/cones will be present, 06/30/24 from 6 am to 7 am. [2024-233]
 

COFFEE COUNTY I-24 (MM 105) construction of an overpass carrying SR-2 (US-41): Phase 1 of I-24 bridge replacement at Exit 105 will continue this week. SR-2 will be reduced to one lane utilizing traffic signal system. The temporary traffic signal will remain in effect until 9/18/2024. Nightly operations for setting beams over I-24 will continue. I-24 will be reduced to one lane in each direction while detouring I-24 traffic on the ramps at the exit 105 interchange. SR-2 will be fully closed at the I-24 interchange with signed detours in place. This nightly work is expected to last until 7/2/2024.
[Bell and Associates Construction, LP/Tullahoma/CNX309]
 

COFFEE COUNTY SR-55 construction from First Avenue (LM 2.0) to SR-16 (US-41A, N. Jackson St, LM 2.6) in Tullahoma: Phase 1 of roadway widening and bridge replacement on SR-55 (Wilson Ave.) will continue this week. Contractor may use temporary lane shifts to complete utility work. Phase 1 traffic shift has reduced lanes from 3 to 2 across the bridge over Rock Creek to start bridge replacement work. Daily flagging operations for utility crossings on SR-55 will start on 6/19.
[Dement Construction Company, LLC/Tullahoma/CNX912]
 

COFFEE COUNTY SR-55 repair of the bridge over the Little Duck River (LM 14.0): Starting 6/26/24, lanes will be reduced to one lane in each direction across the SR-55 bridge over the Little Duck River for bridge repair work. This lane reduction will be in place until work is complete on 7/31/25.
[Mid-State Construction Company, Inc./Tullahoma/CNX412]
 

COFFEE COUNTY SR-55 resurfacing from north of Harper Lane (LM 11.4) to SR-2 (US-41, LM 13.8): There will be nightly lane closures from 7:00 PM to 6:00AM for resurfacing work. One lane in each direction will be always maintained.
[Volunteer Paving, LLC/Tullahoma/CNY096]
 

FRANKLIN COUNTY Old Decherd Road over Wagner Creek (LM 0.3) construction of a bridge: Old Decherd Road is closed at Wagner Creek for bridge replacement. A signed detour is in place. The road closure will be in place for the duration of the project through June 30th, 2025. RESTRICTIONS: Old Decherd Road at Wagner Creek is closed.
[Dement Construction Company, LLC/Tullahoma/CNY068]
 

MARION COUNTY I-24 TDOT Maintenance westbound from MM 148 to MM 149: Work will be performed for culvert repair. I-24 M-M 149 6/24/24 at 9AM-5PM Right Lane
 

MARION COUNTY SR-156 (STATE HWY. 156) TDOT Maintenance eastbound from LM 14.2 to LM 14.4: East bound lane is shut down due to a sink hole. Currently west bound is open with traffic turning left RESTRICTIONS: Until further notice 24 / 7

 

MARION COUNTY I-24 from east of Big Fiery Gizzard Creek (MM 146) to near SR-27 (US-72, MM 152): The contractor will be working on I-24 EB and WB from MM 146 to MM 152 to perform resurfacing operations. Work will be performed Sunday nights through Friday nights from 7 PM – 6 AM each night. No work will occur on Saturday nights. This work will require single lane closures in each direction leaving one lane open to traffic each way. THP and truck mounted attenuators will be on site during the work.
[Rogers Group, Inc./Dunlap/CNX403]
 

SEQUATCHIE COUNTY SR-111 sinkhole and culvert repair at LM 3.3: The contractor is repairing a sinkhole and culvert on SR-111 near L.M. 3.3 in Sequatchie County. The Northbound lanes have been merged and shifted on to a Southbound Lane to move around the sinkhole work area. One lane of the Southbound traffic has been closed leaving one lane open. Please use caution when driving through the work zone.
[Talley Construction Company, Inc./Dunlap/CNY178]
 

WARREN COUNTY SR-1 (US-70S) and SR-380 intersection improvement and SIA to Motlow Advanced Robotics with intersection: Contractor will continue to have intermittent lane closures on SR-380 and SR-1 to work on punch list items. Motorists should expect some delays and use caution through work zone.
[Dement Construction Company, LLC/McMinnville/CNW212]
 

WARREN COUNTY SR-1 (US-70S) resurfacing from east of SR-288 (LM 18.5) to west of SR-136 (LM 23.1): The contractor may have short term shoulder closures to take cores for CIR mix design purposes.
[Tinsley Asphalt, LLC /McMinnville/CNY121]
 

WARREN COUNTY SR-108 resurfacing from the Grundy County line (LM 0.0) to south of SR-287 (LM 2.8): The contractor may have short term shoulder closures in order to install traffic control devices such as message boards and signs for the resurfacing work scheduled to begin around 07/08/24.
[Tinsley Asphalt, LLC /McMinnville/CNY101]
 

WARREN AND WHITE COUNTY SR-136 repair of the bridge over the Caney Fork River LM 2: The bridge will be one lane through most of the project with a one-lane, two-way traffic signal. Motorists should use caution and watch for flaggers. Motorists should expect some delays at the bridge with the traffic signal and traffic utilizing one lane.
[Jamison Construction, LLC/McMinnville/CNX109]
 

DISTRICT 29

BRADLEY COUNTY I-75 at Paul Huff Parkway Interchange modifications: During this reporting period, the contractor will be performing concrete paving on the right shoulder of the I-75 NB off ramp at Paul Huff Parkway. This work will take place behind concrete barrier rail. Right Shoulder of Northbound entrance ramp to I-75, the contractor will be performing grading operations in preparation of concrete paving. Intermittent lane closures on Paul Huff Parkway for construction of Northbound entrance ramp to I-75. Motorists are advised to reduce speed and use caution in the work zone.
[Summers-Taylor, Inc./Cleveland/CNX362]
 

BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): During this reporting period, the contractor will continue grading work and install new storm drainage. Lilac Drive will be closed at the intersection of SR-60 and will remain closed until 06/28/2024. Intermittent flagging operations will take place throughout the project during grading operations. The speed limit in the work zone has been reduced to 35 mph. Motorists are advised to use caution in the work zone and watch for flaggers assisting with traffic control.
[Summers-Taylor, Inc./Cleveland/CNV130]
 

BRADLEY COUNTY SR-74 (OCOEE ST. N.E.) Utility Work southbound from LM 16.29 to LM 16.35: Shoulder and lane closures on SR-74 from Ocoee Street NE to Westview Drive NE. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 06/20/24 through 07/02/24 from 9 am - 2 pm. [2023-560]
 

BRADLEY COUNTY SR-40 (US-64) resurfacing from SR-2 (US-11, US-64, LM 0.0) to near McKamy Street (LM 1.2): The contractor is closing SR-40 Westbound right lane from Bates Street to Edwards Street for the construction of a concrete island. This temporary closure will remain in place until the resurfacing is completed on SR-40 and permanent marking is in place for the new alignment.
[Wright Brothers Construction Company, Inc./Cleveland/CNX132]
 

HAMILTON COUNTY I-24 concrete repair from east of the I-124 (US-27) ramps (MM 179.0) to east of Long Street (MM 178.8): During this reporting period from 9 PM-6 AM, there will be nightly lane closures on I24 and the I24 WB off ramp to US27 NB. During these closures, there is the possibility that ramps might be temporarily closed. During the weekdays from 9 PM-6 AM, there will be 1 lane closed on I24 EB and WB. Also, during this time, US27 SB Traffic onto I24 EB ramp traffic will be detoured onto the Broad St. ramp. The traffic will use the new Frontage Road and get back onto I24 EB at the Market St. on-ramp to I24 EB. Traffic should expect possible long delays during this time and to find alternate routes around this area.
[Summers-Taylor, Inc./Chattanooga West/CNX186]
 

HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: (Note: The contractor will be observing the 4th of July holiday lane closure restrictions, with no lane closures from noon on Wednesday, July 3rd until 6 AM on Monday, July 8th) Nightly lane closures will occur on this project, 9 PM to 6 AM, on I-75 North and South between Exit 1 (East Ridge) and Exit 3A (East Brainerd Road/ SR-320) and on I-24 East and West from Germantown Road to Spring Creek Road, MM182 to MM185, for various construction activities. Uniformed police officers will be present in these work zones to assist with traffic management and to enforce traffic laws. It may also be necessary to do short duration (15 to 30 minutes) rolling roadblocks during the day for patching potholes, clearing debris or to repair guardrail, attenuators, etc. The left lane on North and South Terrace between Belvoir Avenue and Spring Creek Road will be closed for installation of drainage structures, retaining and noise wall construction. Intermittent daytime non-rush hour lane closures may also be necessary throughout the period on South Terrace and North Terrace to work on utilities, street lighting, and various other construction items. All work is weather permitting. Moore Road and McBrien Road bridges over I 24 are closed as well as the entrance and exit ramps to I-24 between Belvoir Avenue and Moore Road. A continuous flow detour using Belvoir Avenue and Spring Creek Road is in place for local traffic. The closures and detour will be in place for approximately 6 months. RESTRICTIONS: Moore Road and McBrien Road over I-24 closed. I-24 Ramps between Belvoir and Moore Road closed.
[Wright Brothers Construction Company, Inc./Maj Prj - Blevins/DB2101]
 

HAMILTON COUNTY SR-2 (E. 23RD ST.) Utility Work both directions from LM 9.69 to LM 9.94: NIGHTTIME (8 pm - 5:30 am) shoulder and lane closure on SR-2 (E. 23rd Street) between 4th Avenue and Dodds Avenue. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels/cones will be present, 01/23/24 through 07/06/24. [2023-192/197]
 

HAMILTON COUNTY SR-2 (LEE HWY.) Utility Work southbound from LM 15.8 to LM 15.83: Shoulder and lane closures on SR-2 (Lee Hwy) from Airport Road to Honest Street. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 06/27/24 through 07/08/24 from 9 am - 3 pm. [2024-357]
 

HAMILTON COUNTY SR-8 (CHEROKEE BLVD.) Utility Work both directions from LM 10 to LM 11: Lane shift for shoulder and lane closures on SR-8 (Cherokee Blvd) between Spring Street and Market Street. Motorists should reduce speed and be prepared to stop. Trucks, signage and barrels/cones will be present, 06/20/24 through 07/22/24 from 9 am to 4 pm. [2023-127]
 

HAMILTON COUNTY I-124 (US-27) from I-24 Interchange to South of the Tennessee River Bridge: During this reporting period, daily lane closures are possible between 9 AM and 3:30 PM as the contractor begins this work. Lane closures can be on West 4th St., Off Ramp ‘M’ & ‘N’ On Ramps ‘M’& ‘R’. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.
[Stansell Electric Company, Inc./Chattanooga East/CNY900]
 

HAMILTON COUNTY I-75 at the Hamilton Place Mall interchange: The SR-153 southbound ramp to I-75 northbound has been reduced to one lane. Traffic shifts have been implemented on I-75 northbound, Shallowford Road entrance ramps, and Shallow Road exit ramps. The speed limit has been reduced on I-75 throughout the project limits. Motorists should use caution as haul trucks and construction vehicles will be present.
[Summers-Taylor, Inc./Chattanooga West/CNX358]
 

HAMILTON COUNTY SR-29 (US-27) resurfacing from Morrison Springs Road (LM 6.1) to SR-153 (LM 11.6): The contractor plans to install permanent pavement markings. This will be performed nightly 7 PM to 6 AM. Work on the ramps is also planned and may require short term ramp closures. If ramp closures are required, they will be performed between 7 PM and 6 AM. The motoring traffic is advised to drive carefully while this work is ongoing.
[Wright Brothers Construction Company, Inc./Chattanooga West/CNX238]
 

HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, for utility and grading work. The flagging operations will be performed on 06/27/24, 06/28/24, 07/01/24, 07/02/24 and 07/03/24 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment.
[Wright Brothers Construction Company, Inc./Chattanooga East/CNT336]
 

HAMILTON COUNTY SR-319 (Hixon Pike) miscellaneous safety improvements from Boy Scout Road (LM 8.5) to Thrasher Pike (LM 9.5): The contractor plans to begin demolition of curb ramps throughout the project. Intermittent right lane closures will be utilized to complete these activities. Motorists should use caution as workers will be present.
[J. M. Hanner Construction Co., Inc./Chattanooga West/CNY109]
 

HAMILTON COUNTY SR-58 resurfacing from SR-153 (LM 4.6) to near Eller Road (LM 6.5): Resurfacing operations are ongoing. Motorists can expect nightly lane closures from 7 PM to 6 AM. Heavy hauling activities can be expected.
[Wright Brothers Construction Company, Inc./Chattanooga West/CNY057]
 

MCMINN COUNTY SR-68 Utility Work both directions from LM 2 to LM 5: Intermittent stoppages as well as shoulder and lane closures on SR-68 between Union Grove Road and County Road 250. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 06/24/24 through 07/02/24 from 9 am to 2 pm. [2024-026]
 

MCMINN COUNTY SR-39 construction of a bridge over Middle Creek (LM 13.4): During this reporting period, the Northbound and Southbound traffic will be reduced to one lane and controlled by traffic signals. County road 567 will be closed to traffic (LOCAL TRAFFIC ONLY) and detoured to SR039. This closure is necessary to perform the bridge replacement. The lane restriction will remain in place until the bridge replacement is completed.
[Whaley Construction, LLC/Chattanooga East/CNX069]
 

MEIGS COUNTY SR-304 Utility Work both directions from LM 14.13 to LM 16.53: Flagging operations on SR-304 between Euchee Road CR 527 and Halfmoon Shores Drive. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and barrels/cones will be present, 06/17/24 through 07/03/24 from 9 am - 2 pm. [2024-040]
 

MEIGS COUNTY SR-68 resurfacing from Rhea County line to McMinn County line: During this reporting period, Daily Lane Closures are possible between 7 AM and 7 PM as the contractor begins this work. Motorists are advised to reduce speed in the work zone and watch for flaggers assisting with traffic control.
[Rogers Group, Inc./Chattanooga East/CNY011]
 

MEIGS COUNTY W. Memorial Drive, Bridge over Decatur Branch, LM 0.37 in Decatur: During this reporting period, the bridge over Decatur Branch on W Memorial Dr. will be closed to all traffic starting on Saturday June 1st, 2024, weather permitting. This closure is necessary to perform the Box Bridge Replacement. Detour routes are posted with signs. This closure will remain in place until the Box Bridge Replacement and associated work is completed. RESTRICTIONS: Box bridge on W Memorial Drive over Decatur Branch is closed for replacement.
[Southern Constructors, Inc./Chattanooga East/CNY099]
 

POLK COUNTY SR-68 construction of bridge over Brush Creek (LM 16.4): During this update period, the contractor will continue grading operation on East side of SR-68. A temporary traffic signal system is active on SR-68 near LM 16.4. The Northbound Lane of SR-68 will be closed in the area controlled by the temporary traffic signal system. Motorists are advised to reduce speed and use caution in the work zone.
[Wright Brothers Construction Company, Inc./Cleveland/CNX347]
 

RHEA COUNTY SR-29 (US-27) resurfacing from north of Payne Lane (LM 11) to near Bradley Street (L.M. 14.6): The contractor plans to perform resurfacing operations 07/01/2024 - 07/03/2024. Daytime temporary lane closures are planned to complete these operations.
[Rogers Group, Inc./Chattanooga West/CNX219]
 

REGION WIDE
 

REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: This contract begins 07/01/24. The contractor may have short term shoulder and/or lane closures to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will always remain open to traffic on the interstate, and flaggers will be present on state routes during any work that is performed.
[Cumberland Guardrail, Inc./McMinnville/CNY105]
 

REGION 2 The random on-call attenuator repair on various Interstate and State Routes: This contract begins 07/01/24. The contractor will be making attenuator repairs at various interstates and state route locations throughout the Region as needed. Motorists should use caution and be prepared for lane closures and flagging operations.
[LU, Inc./McMinnville/CNY104]
 

REGION 2 The retracing of pavement markings with spray thermoplastic and random on-call pavement marking on various Interstate and State Routes.: The contractor will be restriping pavement markings in Cumberland County on SR-28 from LM 10.71 - 15.00, Cumberland County SR-68 from LM 5.20 - 12.55, Cumberland County SR-1 from LM 8.86 - 12.69, White County SR-1 from LM 7.00 - 7.12, White County SR-135 from LM 0.00 - 2.10, White County SR-111 from LM 3.49 - 3.52, Hamilton County SR-8 from LM 11.96 - 15.20, and Hamilton County SR-111 LM 0.22 - 7.35. Motorists are encouraged to use caution when paint crews are present and be mindful of wet pavement markings.
[Reynolds Sealing and Striping, Inc./Cookeville/CNY055]
 

REGION 2 The sweeping on various Interstate and State Routes: There will be an area wide sweeping operation on selected regional state routes and interstates. This activity will be supported by a mobile lane closure. Hours of activity are Sunday through Thursday night between 8 PM and 6 AM during this reporting period.
[Blevins Enterprises, Inc./Chattanooga West/CNX353]
 

REGION 2 preventative and unscheduled maintenance of Chattanooga SmartWay Intelligent Transportation System: The contractor may have short term shoulder and/or lane closures to perform preventative or unscheduled maintenance to the local SmartWay Intelligent Transportation System. At least one travel lane will always remain open to traffic. Flaggers will assist with traffic control as needed.
[Lumin8 Transportation Technologies, LLC/Chattanooga East/CNX270]
 

REGION 2 The installation of longitudinal cable barrier on various Interstate Routes: The contractor will have daytime shoulder closures on interstates throughout region 2 in order to perform cable rail installation. Both travel lanes will always remain open to traffic on the interstate during any daytime work that is performed. However, some nighttime single lane closures will be in place nightly Sundays through Thursdays from 7 PM to 6 AM as needed.
[R.D. Construction, LLC/McMinnville/CNW374]
 

REGION 2 The on-call guardrail repair and new guardrail installation on various Interstate and State Routes: The contractor may have short term shoulder and/or lane closures in order to perform guardrail repair. These closures will take place on the interstate nightly Sunday through Thursday from 7 PM to 6 AM and daily Monday through Friday on state routes. At least one travel lane will always remain open to traffic on the interstate, and flaggers will be present on state routes during any work that is performed.
[Cumberland Guardrail, Inc./McMinnville/CNX096]
 

REGION 2 The random on-call attenuator repair on various Interstate and State Routes: The contractor will be making attenuator repairs at various interstates and state route locations throughout the Region as needed. Motorists should use caution and be prepared for lane closures and flagging operations. This contract ends 06/30/24.
[Site-Safe, LLC/McMinnville/CNX131]
 

REGION 2 The random on-call cable barrier repair on various Interstate and State Routes: The contractor may have short term shoulder closures in order to perform cable rail repair. Both travel lanes will always remain open to traffic on the interstate during any daytime work that is performed. Nighttime closures will be needed occasionally and will be worked nightly Sunday through Thursday from 7 PM to 6 AM as needed.
[Tennessee Guardrail, Inc./McMinnville/CNX312]
 

RESTRICTIONS
 

CUMBERLAND COUNTY - CNX110: Bridge on SR-1 (US-70) over the Obed River is being replaced. The road is closed at LM 12.72.
 

DEKALB COUNTY: The road is closed at LM 0.43 near the Smith - Dekalb County line.
 

JACKSON COUNTY - CNX406: Closed with detour in place.
 

JACKSON COUNTY - CNX111: The road is reduced to one 11’ lane from LM 4.5 – 5.0 using temporary traffic signals to control traffic through the work zone.
 

BLEDSOE COUNTY: No restrictions currently
 

FRANKLIN COUNTY - CNY068: Old Decherd Road at Wagner Creek is closed.
 

MARION COUNTY: Until further notice 24 / 7
 

HAMILTON COUNTY - DB2101: Moore Road and McBrien Road over I-24 closed. I-24 Ramps between Belvoir and Moore Road closed.
 

MEIGS COUNTY - CNY099: Box bridge on W Memorial Drive over Decatur Branch is closed for replacement.

###