Bridge Construction/Closure Details
CONSTRUCTION
Construction of the bridge will be completed at multiple stages. Early Work began in September 2022 and substructure work will begin in January 2023.
Pe-Closure Work: September 2022 – June 2023:
- Utility relocation, Substructure Demo / Erection Demo, sidewalks and overhangs, Shift traffic to four (4) lanes
Complete Closure of Broadway: July 7, 2023 – September 8, 2023
- Superstructure Demo / Erection
All work on the project is expected to be completed by October 2023.
DETOUR
Several detours will be signed for drivers in the downtown area. See the map below - CLICK HERE for an enlarged detour map.
![Broadway Bridge Detour Map_COMBINED_update_v2_11th Broadway Bridge Detour Map_COMBINED_update_v2_11th](/content/tn/tdot/projects/region-3/nashville-broadway-viaduct/bride-closure-details/jcr%3acontent/content/tn_image.img.jpg/1689260869356.jpg)
NOTE: The below closure date has been adjusted to Sept. 8.
![Lane Closure Graphic Template - 1080x1080 - TEMPLATE 2 Lane Closure Graphic Template - 1080x1080 - TEMPLATE 2](/content/tn/tdot/projects/region-3/nashville-broadway-viaduct/bride-closure-details/jcr%3acontent/content/tn_image_970951452.img.png/1694027216904.png)